BURNER TIP,SIZE KB417,INCOLOY
Material 4100077997 · BURNER TIP · Plant 1000
- Material
- 4100077997
- Category
- BURNER TIP
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- C (0 of 1 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 127 d · P80 204 d
- Unit price
- Rp 15.5M (est.)
Recommendation
- 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~127 days; expected demand during lead time 0.0.
- 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 599,096/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~79 days.
Installed on 1 functional locations
0 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-101-COIL08 DILUTION STEAM TO MIXED FEED COIL | C | 1 | 0 | 0.45 |
Lead time and procurement
Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
Never issued in the 17-month history.