BURNER TIP,SIZE RR239,SS304

Material 4100078484 · BURNER TIP · Plant 1000

ALong-leadMonitorInsurance gap
Material
4100078484
Category
BURNER TIP
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
PERMATA INSTRUMEN JAYA PT
Lead time
131 d · P80 204 d
Unit price
Rp 12.3M

Recommendation

  • 1.Forecast 1.6 EA/year: 1.6 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~131 days; expected demand during lead time 0.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Long lead time: 80% of deliveries took up to 204 days and the fastest seen in its category 79 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidateLong-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
100.0%
stockout risk now 45%
Unit price
Rp 12.3M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 25 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-102
CRACKING FURNACE BF-102
A17128.72
PX_BF-104
CRACKING FURNACE BF-104
A12811.58

Lead time and procurement

Lead time 131 ± 68 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
14 May 2025PR06
Regular replenishment
2Rp 12.3M07 Oct 2025146 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
16 Sept 2026MediumPX_BF-104Hot spot at convection BF-104
13 Sept 2026LowPX_BF-104Install cover plate for MCP cracking
07 Sept 2026LowPX_BF-102Thermograph wall BF-102
06 Sept 2026MediumPX_BF-102Decoking follow up BF-102
04 Sept 2026MediumPX_BF-104Replace burner tip BF-104
03 Sept 2026MediumPX_BF-102Replace lamp as per PM finding
01 Sept 2026MediumPX_BF-104Install scaffolding at BF-104
30 Aug 2026HighPX_BF-102Painting BF-102

Recent goods issues

Never issued in the 17-month history.