BURNER TIP,TYPE FT176,NBR
Material 4100078529 · BURNER TIP · Plant 1000
AReorderCriticalStockout
- Material
- 4100078529
- Category
- BURNER TIP
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 127 d · P80 204 d
- Unit price
- Rp 15.5M (est.)
Recommendation
- 1.Forecast 1.9 EA/year: 1.9 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~127 days; expected demand during lead time 0.6.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
- 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 93.0M · order by 01 Oct 2026
Expected arrival ≈ 127 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 48%
Unit price
Rp 15.5M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 31 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.
Installed on 2 functional locations
1 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1 | 41 | 14.58 |
Lead time and procurement
Lead time 127 ± 68 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 19 Sept 2026 | Medium | PX_BF-106 | Cleaning burner BF-106 |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-106 | Install cover plate BF-106 |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 14 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 29 Jun 2025 | 1 | 203000034428 | Turnaround |