ANCHOR,REFRACTORY,MODEL OE349,A182F11

Material 4100079000 · ANCHOR · Plant 1000

AMonitorCritical insurance spare
Material
4100079000
Category
ANCHOR
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 7 FuncLocs A/B)
Supplier
No PO history
Lead time
68 d · P80 81 d
Unit price
Rp 41,974 (est.)

Recommendation

  • 1.Forecast 1,928 EA/year: 1,928 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~68 days; expected demand during lead time 357.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,750, order up to 2,581.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 7 FuncLoc(s), 5 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
15 / 0
no open PO
Today Min / Max
10 / 16
static parameters in BoM
Rec. Min (reorder point)
1,750
safety stock 1,394
Rec. Max
2,581
order qty 831
Service level
99.9%
stockout risk now 64%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 70 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 7 functional locations

5 with criticality A/B · 15,024 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-105
CRACKING FURNACE BF-105
A1,50011442.86
PX_BF-112
CRACKING FURNACE BF-112
A4007327.01
PX_BF-102
CRACKING FURNACE BF-102
A1,5007128.72
PX_BF-103
CRACKING FURNACE BF-103
A5,0373814.58
PX_BF-111
CRACKING FURNACE BF-111
A1,500239.01
PX_BF-108
CRACKING FURNACE BF-108
S5,037239.44
PX_BF-101
CRACKING FURNACE BF-101
S5083.02

Lead time and procurement

Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026HighPX_BF-105Repair refractory crack BF-105
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026HighPX_BF-108Leak from packing
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
20 Sept 2026MediumPX_BF-103Leak from packing

Recent goods issues

Never issued in the 17-month history.