ANCHOR,REFRACTORY,SIZE TY222,A182F11
Material 4100079028 · ANCHOR · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100079028
- Category
- ANCHOR
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 8 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 68 d · P80 81 d
- Unit price
- Rp 41,974 (est.)
Recommendation
- 1.Forecast 3,303 EA/year: 3,303 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~68 days; expected demand during lead time 611.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,753, order up to 2,840.
- 4.On hand 1,040 + on order 0 is at or below the reorder point: order 1,800 now.
- 5.Installed on 8 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
1,800 EA
Rp 75.6M · order by 01 Oct 2026
Expected arrival ≈ 68 days
Price estimatedLead time estimated
On hand / on order
1,040 / 0
no open PO
Today Min / Max
39 / 111
static parameters in BoM
Rec. Min (reorder point)
1,753
safety stock 1,143
Rec. Max
2,840
order qty 1,087
Service level
99.9%
stockout risk now 12%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 200 days ago, 71 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 15.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 8 functional locations
6 with criticality A/B · 3,860 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-106 CRACKING FURNACE BF-106 | A | 50 | 82 | 30.86 |
| PX_BF-112 CRACKING FURNACE BF-112 | A | 50 | 73 | 27.01 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 120 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 1,500 | 29 | 11.58 |
| PX_BF-107 CRACKING FURNACE BF-107 | A | 400 | 23 | 9.01 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 120 | 23 | 9.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 1,500 | 41 | 14.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 120 | 8 | 3.02 |
Lead time and procurement
Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 30 Sept 2026 | Medium | PX_BF-112 | Install cover plate BF-112 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Low | PX_BF-112 | Painting BF-112 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 27 Sept 2026 | Medium | PX_BF-112 | Repair insulation BF-112 |
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Mar 2026 | 50 | 201000007030 | Corrective |
| 27 Feb 2026 | 200 | 201000037279 | Corrective |