Sparely
DU

ANCHOR,REFRACTORY,SIZE YM635,CS

Material 4100079068 · ANCHOR · Plant 1000

AReorderCriticalBelow reorder point
Material
4100079068
Category
ANCHOR
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
68 d · P80 81 d
Unit price
Rp 41,974 (est.)

Recommendation

  • 1.Forecast 6,294 EA/year: 6,294 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~68 days; expected demand during lead time 1,164.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5,000, order up to 6,500.
  • 4.On hand 1,000 + on order 0 is at or below the reorder point: order 5,500 now.
  • 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
5,500 EA
Rp 230.9M · order by 01 Oct 2026
Expected arrival ≈ 68 days
Price estimatedLead time estimated
On hand / on order
1,000 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5,000
safety stock 3,836
Rec. Max
6,500
order qty 1,500
Service level
99.9%
stockout risk now 32%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 81 days ago, 17 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 2 functional locations

2 with criticality A/B · 520 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-104
CRACKING FURNACE BF-104
A1202811.58
PX_BF-107
CRACKING FURNACE BF-107
A400239.01

Lead time and procurement

Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
21 Sept 2026MediumPX_BF-104Cleaning burner BF-104
16 Sept 2026MediumPX_BF-104Hot spot at convection BF-104
13 Sept 2026LowPX_BF-104Install cover plate for MCP cracking
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
04 Sept 2026MediumPX_BF-104Replace burner tip BF-104
01 Sept 2026MediumPX_BF-104Install scaffolding at BF-104
29 Aug 2026HighPX_BF-104Leak from packing
15 Aug 2026MediumPX_BF-107Hot spot at convection BF-107
08 Aug 2026LowPX_BF-104[MSI-B-26-MZB-191] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
12 Jul 20261,000201000032968Corrective