ANCHOR,REFRACTORY,MODEL WD458,SS304

Material 4100079201 · ANCHOR · Plant 1000

AMonitorCritical insurance spare
Material
4100079201
Category
ANCHOR
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
68 d · P80 81 d
Unit price
Rp 41,974 (est.)

Recommendation

  • 1.Forecast 872 EA/year: 872 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~68 days; expected demand during lead time 161.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,050, order up to 1,609.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
11 / 0
no open PO
Today Min / Max
10 / 15
static parameters in BoM
Rec. Min (reorder point)
1,050
safety stock 889
Rec. Max
1,609
order qty 559
Service level
99.9%
stockout risk now 37%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 38 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 4 functional locations

2 with criticality A/B · 3,240 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-102
CRACKING FURNACE BF-102
A1207128.72
PX_BF-103
CRACKING FURNACE BF-103
A1,5003814.58
PX_BF-110
CRACKING FURNACE BF-110
S1204114.58
PX_BF-101
CRACKING FURNACE BF-101
S1,50083.02

Lead time and procurement

Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
17 Sept 2026MediumPX_BF-110Install scaffolding at BF-110
15 Sept 2026MediumPX_BF-103Replace lamp as per PM finding
15 Sept 2026MediumPX_BF-110Decoking follow up BF-110
14 Sept 2026MediumPX_BF-101Replace lamp as per PM finding
11 Sept 2026MediumPX_BF-103Decoking follow up BF-103

Recent goods issues

Never issued in the 17-month history.