ANCHOR,REFRACTORY,MODEL WD458,SS304
Material 4100079201 · ANCHOR · Plant 1000
AMonitorCritical insurance spare
- Material
- 4100079201
- Category
- ANCHOR
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 68 d · P80 81 d
- Unit price
- Rp 41,974 (est.)
Recommendation
- 1.Forecast 872 EA/year: 872 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~68 days; expected demand during lead time 161.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1,050, order up to 1,609.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
11 / 0
no open PO
Today Min / Max
10 / 15
static parameters in BoM
Rec. Min (reorder point)
1,050
safety stock 889
Rec. Max
1,609
order qty 559
Service level
99.9%
stockout risk now 37%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 38 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.
Installed on 4 functional locations
2 with criticality A/B · 3,240 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-102 CRACKING FURNACE BF-102 | A | 120 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 1,500 | 38 | 14.58 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 120 | 41 | 14.58 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1,500 | 8 | 3.02 |
Lead time and procurement
Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
Recent goods issues
Never issued in the 17-month history.