ANCHOR,REFRACTORY,TYPE UL206,SS304

Material 4100079353 · ANCHOR · Plant 1000

AReorderNormalTAM reserve
Material
4100079353
Category
ANCHOR
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
68 d · P80 81 d
Unit price
Rp 41,974 (est.)

Recommendation

  • 1.Forecast 430 EA/year: 430 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~68 days; expected demand during lead time 80.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 700, order up to 1,092.
  • 4.On hand 334 + on order 0 is at or below the reorder point: order 758 now.
  • 5.Used only during the last turnaround (500 EA): keep it for the next one instead of treating it as slow-moving.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
758 EA
Rp 31.8M · order by 01 Oct 2026
Expected arrival ≈ 68 days
Last turnaround used 500Price estimatedLead time estimated
On hand / on order
334 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
700
safety stock 621
Rec. Max
1,092
order qty 392
Service level
99.8%
stockout risk now 20%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (500 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 706.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 2 functional locations

1 with criticality A/B · 520 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-112
CRACKING FURNACE BF-112
A4007327.01
PX_BF-101
CRACKING FURNACE BF-101
S12083.02

Lead time and procurement

Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_BF-112Install cover plate BF-112
29 Sept 2026LowPX_BF-112Painting BF-112
27 Sept 2026MediumPX_BF-112Repair insulation BF-112
17 Sept 2026MediumPX_BF-112Cleaning burner BF-112
14 Sept 2026MediumPX_BF-101Replace lamp as per PM finding
04 Sept 2026HighPX_BF-112Install scaffolding at BF-112
01 Sept 2026MediumPX_BF-112Replace burner tip BF-112
01 Sept 2026MediumPX_BF-112Replace burner tip BF-112
31 Aug 2026MediumPX_BF-112Install cover plate for MCP cracking
17 Aug 2026MediumPX_BF-112Painting BF-112

Recent goods issues

Posting dateQtyOrderOrder type
21 Dec 2025500203000033807Turnaround