ANCHOR,REFRACTORY,MODEL YO985,SS316

Material 4100079652 · ANCHOR · Plant 1000

AMonitorCritical insurance spare
Material
4100079652
Category
ANCHOR
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
68 d · P80 81 d
Unit price
Rp 41,974 (est.)

Recommendation

  • 1.Forecast 338 EA/year: 338 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~68 days; expected demand during lead time 62.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 700, order up to 1,050.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
9 / 0
no open PO
Today Min / Max
3 / 9
static parameters in BoM
Rec. Min (reorder point)
700
safety stock 638
Rec. Max
1,050
order qty 350
Service level
99.9%
stockout risk now 16%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 19 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 555.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 2 functional locations

2 with criticality A/B · 1,550 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-103
CRACKING FURNACE BF-103
A503814.58
PX_BF-107
CRACKING FURNACE BF-107
A1,500239.01

Lead time and procurement

Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
15 Sept 2026MediumPX_BF-103Replace lamp as per PM finding
11 Sept 2026MediumPX_BF-103Decoking follow up BF-103
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
26 Aug 2026MediumPX_BF-103Replace lamp as per PM finding
26 Aug 2026MediumPX_BF-103Hot spot at convection BF-103
15 Aug 2026MediumPX_BF-107Hot spot at convection BF-107

Recent goods issues

Never issued in the 17-month history.