Sparely
DU

ANCHOR,REFRACTORY,TYPE XW230,SS316

Material 4100080485 · ANCHOR · Plant 1000

AReorderCriticalStockout
Material
4100080485
Category
ANCHOR
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
68 d · P80 81 d
Unit price
Rp 41,974 (est.)

Recommendation

  • 1.Forecast 596 EA/year: 596 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~68 days; expected demand during lead time 110.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 400, order up to 862.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 862 now.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
862 EA
Rp 36.2M · order by 01 Oct 2026
Expected arrival ≈ 68 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
400
safety stock 290
Rec. Max
862
order qty 462
Service level
100.0%
stockout risk now 89%
Unit price
Rp 41,974
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 93 days ago, 28 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~27 days.

Installed on 2 functional locations

1 with criticality A/B · 3,000 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-106
CRACKING FURNACE BF-106
A1,5008230.86
PX_BF-108
CRACKING FURNACE BF-108
S1,500239.44

Lead time and procurement

Lead time 68 ± 20 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
28 Sept 2026LowPX_BF-106Peep door broken BF-106
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026HighPX_BF-108Leak from packing
19 Sept 2026MediumPX_BF-106Cleaning burner BF-106
15 Sept 2026MediumPX_BF-106Install cover plate BF-106
14 Sept 2026LowPX_BF-106Peep door broken BF-106
10 Sept 2026MediumPX_BF-106Replace burner tip BF-106
10 Sept 2026MediumPX_BF-108[MSI-B-26-JJB-193] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
30 Jun 202650201000011761Corrective