BEARING,JOURNAL,TYPE PW729,SS304

Material 4100080809 · BEARING · Plant 1000

ALong-leadMaintainHealthy
Material
4100080809
Category
BEARING
Base unit
SET
MRP type
Stock Item
Criticality
A (4 of 6 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
119 d · P80 127 d
Unit price
Rp 242.1M

Recommendation

  • 1.Forecast 5.2 SET/year: 4.5 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~119 days; expected demand during lead time 2.2 (incl. 0.7 planned).
  • 3.A 98.3% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 6.
  • 4.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
  • 6.ML early warning: 60% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceOpen POPlanned demand in lead time
On hand / on order
2 / 4
next delivery 04 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 3
Rec. Max
6
order qty 1
Service level
98.3%
stockout risk now 0%
Unit price
Rp 242.1M
PO history
ML early warning: 60% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 81 days ago, 4 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 6 functional locations

4 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-317B
RICH AMINE FAN
A141.85
PX_KC-752A
CONDENSATE BLOWER
A141.85
PX_KC-235D
DEMIN WATER FAN
A121.00
PX_KC-371B
BOTTOM FAN
B100.57
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KC-422A
C4 PRODUCT BLOWER
S162.71

Lead time and procurement

Lead time 119 ± 40 days (PO history + category, 2 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
11 Aug 2026PR06
Regular replenishment
2Rp 242.2M24 May 2027
open
286 d
11 Jun 2026PR05
Project / turnaround
2Rp 242.0M04 Nov 2026
open
146 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_KC-235DCompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Jul 2026MediumPX_KC-422AKC-422A high vibration
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
04 Jul 2026LowPX_KC-317BReplace lamp as per PM finding
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026MediumPX_KC-317BKC-317B lube oil filter DP high
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland

Recent goods issues

Posting dateQtyOrderOrder type
12 Jul 20261201000020631Corrective