BEARING,JOURNAL,SIZE NK74,A182F11

Material 4100080954 · BEARING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100080954
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 4 FuncLocs A/B)
Supplier
DUTA SEJAHTERA ABADI PT
Lead time
123 d · P80 127 d
Unit price
Rp 533.7M

Recommendation

  • 1.Forecast 2.0 SET/year: 2.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~123 days; expected demand during lead time 0.7.
  • 3.A 96.8% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.On hand 0 + on order 2 is at or below the reorder point: order 1 now.
  • 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
1 SET
Rp 533.7M · order by 01 Oct 2026
Expected arrival ≈ 123 days
Long-leadConvert to Stock ItemLast turnaround used 1Single sourceOpen PO
On hand / on order
0 / 2
next delivery 08 Apr 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
96.8%
stockout risk now 3%
Unit price
Rp 533.7M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 163 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 990.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 4 functional locations

4 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-247A
SLOP OIL FAN
A194.00
PX_KC-464A
CONDENSATE BLOWER
A421.43
PX_KC-223
RECYCLE ETHANE FAN
A100.57
PX_KC-621
SEAL OIL FAN
A100.57

Lead time and procurement

Lead time 123 ± 40 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
01 Aug 2026PR06
Regular replenishment
1Rp 511.3M26 Apr 2028
open
634 d
16 May 2026PR06
Regular replenishment
1Rp 556.0M08 Apr 2027
open
327 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Aug 2026HighPX_KC-247AInspect coupling KC-247A
14 Jul 2026MediumPX_KC-247AReplace lamp as per PM finding
29 Jun 2026LowPX_KC-247AKC-247A high vibration
04 Jun 2026LowPX_KC-247AKC-247A bearing temp high
06 Apr 2026MediumPX_KC-247AKC-247A bearing temp high
20 Nov 2025MediumPX_KC-247AReplace lamp as per PM finding
02 Oct 2025MediumPX_KC-464AKC-464A lube oil filter DP high
22 Aug 2025LowPX_KC-247AOverhaul
09 Aug 2025HighPX_KC-247AInspect coupling KC-247A
25 Jul 2025MediumPX_KC-464AKC-464A lube oil filter DP high

Recent goods issues

Posting dateQtyOrderOrder type
21 Apr 20261201000014672Corrective
17 Nov 20251203000006868Turnaround
22 Aug 20251201000015115Corrective