BEARING,JOURNAL,SIZE NK74,A182F11
Material 4100080954 · BEARING · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100080954
- Category
- BEARING
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (4 of 4 FuncLocs A/B)
- Supplier
- DUTA SEJAHTERA ABADI PT
- Lead time
- 123 d · P80 127 d
- Unit price
- Rp 533.7M
Recommendation
- 1.Forecast 2.0 SET/year: 2.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~123 days; expected demand during lead time 0.7.
- 3.A 96.8% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.On hand 0 + on order 2 is at or below the reorder point: order 1 now.
- 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
1 SET
Rp 533.7M · order by 01 Oct 2026
Expected arrival ≈ 123 days
Long-leadConvert to Stock ItemLast turnaround used 1Single sourceOpen PO
On hand / on order
0 / 2
next delivery 08 Apr 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
96.8%
stockout risk now 3%
Unit price
Rp 533.7M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 163 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 990.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 4 functional locations
4 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-247A SLOP OIL FAN | A | 1 | 9 | 4.00 |
| PX_KC-464A CONDENSATE BLOWER | A | 4 | 2 | 1.43 |
| PX_KC-223 RECYCLE ETHANE FAN | A | 1 | 0 | 0.57 |
| PX_KC-621 SEAL OIL FAN | A | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 123 ± 40 days (PO history + category, 1 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Aug 2026 | PR06 Regular replenishment | 1 | Rp 511.3M | 26 Apr 2028 open | 634 d |
| 16 May 2026 | PR06 Regular replenishment | 1 | Rp 556.0M | 08 Apr 2027 open | 327 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 Aug 2026 | High | PX_KC-247A | Inspect coupling KC-247A |
| 14 Jul 2026 | Medium | PX_KC-247A | Replace lamp as per PM finding |
| 29 Jun 2026 | Low | PX_KC-247A | KC-247A high vibration |
| 04 Jun 2026 | Low | PX_KC-247A | KC-247A bearing temp high |
| 06 Apr 2026 | Medium | PX_KC-247A | KC-247A bearing temp high |
| 20 Nov 2025 | Medium | PX_KC-247A | Replace lamp as per PM finding |
| 02 Oct 2025 | Medium | PX_KC-464A | KC-464A lube oil filter DP high |
| 22 Aug 2025 | Low | PX_KC-247A | Overhaul |
| 09 Aug 2025 | High | PX_KC-247A | Inspect coupling KC-247A |
| 25 Jul 2025 | Medium | PX_KC-464A | KC-464A lube oil filter DP high |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Apr 2026 | 1 | 201000014672 | Corrective |
| 17 Nov 2025 | 1 | 203000006868 | Turnaround |
| 22 Aug 2025 | 1 | 201000015115 | Corrective |