BEARING,JOURNAL,MODEL DS290,A105
Material 4100081001 · BEARING · Plant 1000
AReduceNon-moving
- Material
- 4100081001
- Category
- BEARING
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 55 d · P80 127 d
- Unit price
- Rp 219.3M (est.)
Recommendation
- 1.Forecast 2.6 SET/year: 0.4 unplanned (installed-base failure prior (no history)) + 2.1 from the maintenance plan.
- 2.Lead time ~55 days; expected demand during lead time 0.1.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Stock 4 exceeds the level to keep (2) by 2.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 198.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 4 functional locations
2 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_KC-620A DEMIN WATER AIR COMPRESSOR | B | 3 | 2 | 1.00 |
| PX_KT-447 TURBINE FOR KC-447 | S | 1 | 13 | 6.24 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Aug 2027 | PX_KC-620A | Compressor major overhaul | 2.15 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 13 May 2026 | Low | PX_KT-447 | KT-447 trip test |
| 19 Apr 2026 | Low | PX_KT-447 | Follow up after steam upset KT-447 |
| 30 Mar 2026 | Low | PX_KT-447 | Leak from packing |
| 28 Mar 2026 | Medium | PX_KT-447 | Follow up after steam upset KT-447 |
| 14 Mar 2026 | Medium | PX_KT-447 | KT-447 steam leak at gland |
| 14 Jan 2026 | Medium | PX_KT-447 | Follow up after steam upset KT-447 |
| 04 Jan 2026 | Medium | PX_KT-513 | KT-513 governor valve hunting |
| 15 Dec 2025 | Medium | PX_KC-620A | Inspect coupling KC-620A |
Recent goods issues
Never issued in the 17-month history.