BEARING,JOURNAL,SIZE MW654,GRAPHITE

Material 4100081040 · BEARING · Plant 1000

AMonitorInsurance gap
Material
4100081040
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (2 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 219.3M (est.)

Recommendation

  • 1.Forecast 0.4 SET/year: 0.4 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~55 days; expected demand during lead time 0.1.
  • 3.A 93.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
93.9%
stockout risk now 6%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 205.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 4 functional locations

2 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-308B
TURBINE FOR KC-308B
A401.10
PX_KC-624A
RECYCLE ETHANE BLOWER
B152.28
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KC-216B
LEAN AMINE FAN
S110.57

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
21 Aug 2026MediumPX_KC-624AKC-624A high vibration
10 Aug 2026MediumPX_KC-624ALeak from packing
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
18 Jun 2026LowPX_KC-624AOverhaul
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland

Recent goods issues

Never issued in the 17-month history.