BEARING,JOURNAL,SIZE RG734,NBR

Material 4100081716 · BEARING · Plant 1000

ALong-leadMonitorStockout
Material
4100081716
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
102 d · P80 127 d
Unit price
Rp 477.1M

Recommendation

  • 1.Forecast 1.1 SET/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~102 days; expected demand during lead time 0.3.
  • 3.A 96.5% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 18 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
96.5%
stockout risk now 0%
Unit price
Rp 477.1M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 290 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 518.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-308B
TURBINE FOR KC-308B
A101.10

Lead time and procurement

Lead time 102 ± 40 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
19 Feb 2026PR06
Regular replenishment
1Rp 471.1M18 Oct 2026
open
241 d
08 Jul 2025PR05
Project / turnaround
1Rp 483.0M13 Oct 2027
open
827 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
12 Dec 2025LowPX_KT-460BKT-460B governor valve hunting
27 Jul 2025MediumPX_KT-460BFollow up after steam upset KT-460B

Recent goods issues

Posting dateQtyOrderOrder type
15 Dec 20251201000012406Corrective