BEARING,THRUST PAD,SIZE KZ121,GRAPHITE
Material 4100082772 · BEARING · Plant 1000
AReorderCriticalSlow-moving
- Material
- 4100082772
- Category
- BEARING
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (3 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 55 d · P80 127 d
- Unit price
- Rp 219.3M (est.)
Recommendation
- 1.Forecast 9.3 SET/year: 8.6 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~55 days; expected demand during lead time 2.0 (incl. 0.7 planned).
- 3.A 92.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 6 now.
- 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
6 SET
Rp 1.3B · order by 01 Oct 2026
Expected arrival ≈ 55 days
Needs Management sign-off before it reaches the PR draft
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 2
Rec. Max
7
order qty 3
Service level
92.9%
stockout risk now 35%
Unit price
Rp 219.3M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 258 days ago, 4 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 4 functional locations
3 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KC-452 HYDROGEN FAN | A | 1 | 6 | 2.71 |
| PX_KC-235D DEMIN WATER FAN | A | 1 | 2 | 1.00 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
Lead time and procurement
Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_KC-235D | Compressor major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 05 Sept 2026 | Medium | PX_KC-452 | Overhaul |
| 05 Sept 2026 | Medium | PX_KC-452 | Inspect coupling KC-452 |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 26 Mar 2026 | Medium | PX_KT-856A | KT-856A steam leak at gland |
| 20 Jan 2026 | Medium | PX_KC-452 | Replace lamp as per PM finding |
| 09 Jan 2026 | Medium | PX_KT-202 | KT-202 governor valve hunting |
| 20 Nov 2025 | Medium | PX_KT-856A | KT-856A governor valve hunting |
| 16 Nov 2025 | Low | PX_KT-856A | Install scaffolding at KT-856A |
| 11 Nov 2025 | Medium | PX_KC-235D | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Jan 2026 | 3 | 201000014196 | Corrective |