SEAL,LABYRINTH,MODEL HZ113,PTFE

Material 4100084471 · SEAL · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100084471
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (11 of 22 FuncLocs A/B)
Supplier
PERMATA INSTRUMEN MAKMUR PT
Lead time
137 d · P80 213 d
Unit price
Rp 175.9M

Recommendation

  • 1.Forecast 11 SET/year: 9.6 unplanned (credibility blend: own history + installed-base prior) + 1.4 from the maintenance plan.
  • 2.Lead time ~137 days; expected demand during lead time 4.3 (incl. 0.7 planned).
  • 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 12.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 12 now.
  • 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 22 FuncLoc(s), 11 of them criticality A/B.
  • 7.ML early warning: 57% probability of demand in the next 90 days.
Proposed purchase requisition
12 SET
Rp 2.1B · order by 01 Oct 2026
Expected arrival ≈ 137 days
Needs Management sign-off before it reaches the PR draft
Long-leadML early warningConvert to Stock ItemSingle sourcePlanned demand in lead time
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 7
Rec. Max
12
order qty 1
Service level
99.6%
stockout risk now 96%
Unit price
Rp 175.9M
PO history
ML early warning: 57% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 395 days ago, 14 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 14.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 22 functional locations

11 with criticality A/B · 24 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-536A
LUBE OIL BLOWER
A1114.42
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-452
HYDROGEN FAN
A162.71
PX_KC-317B
RICH AMINE FAN
A141.85
PX_KC-464A
CONDENSATE BLOWER
A121.43
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KC-155D
CAUSTIC BLOWER
A100.57
PX_KC-618B
WASH WATER BLOWER
A100.57
PX_KC-669
DEMIN WATER BLOWER
A100.57
PX_KC-620A
DEMIN WATER AIR COMPRESSOR
B121.00
PX_KC-371B
BOTTOM FAN
B100.57
PX_KT-447
TURBINE FOR KC-447
S1136.24

Lead time and procurement

Lead time 137 ± 65 days (PO history + category, 2 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
10 Jun 2026PR03
Regular replenishment
2Rp 173.6M21 Sept 2026103 d
01 Sept 2025PR06
Regular replenishment
2Rp 178.2M10 Jan 2026131 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
01 Aug 2027PX_KC-620ACompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
22 Sept 2026HighPX_KC-536AOverhaul
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
05 Sept 2026MediumPX_KC-452Overhaul
05 Sept 2026MediumPX_KC-452Inspect coupling KC-452
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Aug 2026HighPX_KC-536AKC-536A bearing temp high
26 Jul 2026MediumPX_KC-365CInspect coupling KC-365C
24 Jul 2026HighPX_KC-536AInstall scaffolding at KC-536A
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A

Recent goods issues

Posting dateQtyOrderOrder type
01 Sept 20251201000038656Corrective
11 Jul 20251201000000144Corrective
Sparely