SEAL,LABYRINTH,MODEL ZU580,PTFE

Material 4100084528 · SEAL · Plant 1000

AReorderCriticalStockout
Material
4100084528
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (3 of 6 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 5.0 SET/year: 5.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~150 days; expected demand during lead time 2.1.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 8.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 8 now.
  • 5.Installed on 6 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
8 SET
Rp 756.7M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 5
Rec. Max
8
order qty 1
Service level
99.9%
stockout risk now 87%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 304 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 6 functional locations

3 with criticality A/B · 9 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-778A
CONDENSATE COMPRESSOR
A131.43
PX_KC-624A
RECYCLE ETHANE BLOWER
B152.28
PX_KT-447
TURBINE FOR KC-447
S3136.24
PX_KC-830D
FLUSHING OIL BLOWER
S141.85
PX_KT-624A
TURBINE FOR KC-624A
S232.39

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
21 Aug 2026MediumPX_KC-624AKC-624A high vibration
10 Aug 2026MediumPX_KC-624ALeak from packing
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
18 Jun 2026LowPX_KC-624AOverhaul
04 Jun 2026HighPX_KC-778AInspect coupling KC-778A
31 May 2026LowPX_KC-830DKC-830D high vibration
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447

Recent goods issues

Posting dateQtyOrderOrder type
01 Dec 20251201000010935Corrective