SEAL,LABYRINTH,SIZE KV508,A105
Material 4100084561 · SEAL · Plant 1000
AReorderNormalCritical insurance spare
- Material
- 4100084561
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 94.6M (est.)
Recommendation
- 1.Forecast 1.2 SET/year: 0.4 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~150 days; expected demand during lead time 0.9 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 2 now.
- 5.No issue in 17 months, but it protects critical equipment: keep it.
- 6.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
2 SET
Rp 189.2M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.9%
stockout risk now 2%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 676.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 5 functional locations
3 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 3 | 5 | 1.85 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
| PX_KT-264A TURBINE FOR KC-264A | S | 1 | 4 | 2.39 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 02 Jul 2026 | High | PX_KC-222B | Replace lamp as per PM finding |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
| 26 Mar 2026 | Medium | PX_KT-856A | KT-856A steam leak at gland |
| 05 Feb 2026 | Medium | PX_KC-222B | Install scaffolding at KC-222B |
| 09 Jan 2026 | Medium | PX_KT-202 | KT-202 governor valve hunting |
| 01 Jan 2026 | Low | PX_KC-222B | KC-222B high vibration |
| 20 Nov 2025 | Medium | PX_KT-856A | KT-856A governor valve hunting |
Recent goods issues
Never issued in the 17-month history.