SEAL,LABYRINTH,SIZE KV508,A105

Material 4100084561 · SEAL · Plant 1000

AReorderNormalCritical insurance spare
Material
4100084561
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 1.2 SET/year: 0.4 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 0.9 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 2 now.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
2 SET
Rp 189.2M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.9%
stockout risk now 2%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 676.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 5 functional locations

3 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-222B
LEAN AMINE COMPRESSOR
A351.85
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KT-202
TURBINE FOR KC-202
S142.81
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
02 Jul 2026HighPX_KC-222BReplace lamp as per PM finding
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
26 Mar 2026MediumPX_KT-856AKT-856A steam leak at gland
05 Feb 2026MediumPX_KC-222BInstall scaffolding at KC-222B
09 Jan 2026MediumPX_KT-202KT-202 governor valve hunting
01 Jan 2026LowPX_KC-222BKC-222B high vibration
20 Nov 2025MediumPX_KT-856AKT-856A governor valve hunting

Recent goods issues

Never issued in the 17-month history.