SEAL,LABYRINTH,MODEL WQ711,A105
Material 4100084595 · SEAL · Plant 1000
ALong-leadReduceExcess
- Material
- 4100084595
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (3 of 8 FuncLocs A/B)
- Supplier
- RAJAWALI REFRAKTORI PRATAMA PT
- Lead time
- 156 d · P80 213 d
- Unit price
- Rp 34.8M
Recommendation
- 1.Forecast 12 SET/year: 12 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~156 days; expected demand during lead time 5.0.
- 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 14, order up to 17.
- 4.Stock 145 exceeds the level to keep (17) by 128.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 8 FuncLoc(s), 3 of them criticality A/B.
Long-leadSingle source
On hand / on order
145 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
14
safety stock 10
Rec. Max
17
order qty 3
Service level
99.6%
stockout risk now 0%
Unit price
Rp 34.8M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 25 days ago, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 8.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 8 functional locations
3 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_KC-426D RICH AMINE BLOWER | A | 1 | 0 | 0.57 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KC-773A REFLUX COMPRESSOR | S | 1 | 25 | 9.99 |
| PX_KC-422A C4 PRODUCT BLOWER | S | 1 | 6 | 2.71 |
| PX_KC-216B LEAN AMINE FAN | S | 1 | 1 | 0.57 |
| PX_KC-373 SPENT CAUSTIC BLOWER | S | 1 | 1 | 1.00 |
| PX_KT-875 TURBINE FOR KC-875 | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 156 ± 65 days (PO history + category, 1 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 05 Jan 2026 | PR06 Regular replenishment | 1 | Rp 34.8M | 27 Jun 2026 | 173 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 15 Sept 2026 | Low | PX_KC-773A | Install scaffolding at KC-773A |
| 23 Aug 2026 | Low | PX_KC-773A | KC-773A bearing temp high |
| 10 Aug 2026 | Low | PX_KC-773A | KC-773A high vibration |
| 09 Aug 2026 | Medium | PX_KC-773A | Inspect coupling KC-773A |
| 03 Aug 2026 | Medium | PX_KC-773A | Leak from packing |
| 20 Jul 2026 | Medium | PX_KC-773A | KC-773A high vibration |
| 13 Jul 2026 | Low | PX_KC-773A | KC-773A lube oil filter DP high |
| 08 Jul 2026 | Medium | PX_KC-422A | KC-422A high vibration |
| 07 Jul 2026 | Medium | PX_KC-773A | KC-773A lube oil filter DP high |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 06 Sept 2026 | 2 | 201000023966 | Corrective |