Sparely
DU

SEAL,LABYRINTH,TYPE NS869,SS304

Material 4100084723 · SEAL · Plant 1000

AReorderCriticalStockout
Material
4100084723
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 2.5 SET/year: 2.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~150 days; expected demand during lead time 1.0.
  • 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
  • 5.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
5 SET
Rp 472.9M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
5
order qty 1
Service level
99.6%
stockout risk now 64%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 353 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 4 functional locations

4 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-396
WASH WATER BLOWER
A131.43
PX_KT-308B
TURBINE FOR KC-308B
A101.10

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
17 May 2026LowPX_KC-396Overhaul
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A

Recent goods issues

Posting dateQtyOrderOrder type
13 Oct 20251201000030049Corrective