SEAL,LABYRINTH,TYPE BG775,A182F11

Material 4100084751 · SEAL · Plant 1000

ALong-leadMaintainInsurance gap
Material
4100084751
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (2 of 4 FuncLocs A/B)
Supplier
DUTA SEJAHTERA ABADI PT
Lead time
179 d · P80 213 d
Unit price
Rp 228.6M

Recommendation

  • 1.Forecast 0.5 SET/year: 0.5 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~179 days; expected demand during lead time 0.2.
  • 3.A 97.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 26 Nov 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
97.7%
stockout risk now 0%
Unit price
Rp 228.6M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 713.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 4 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-308B
REFLUX BLOWER
A162.28
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-383A
TURBINE FOR KC-383A
S373.67
PX_KT-202
TURBINE FOR KC-202
S142.81

Lead time and procurement

Lead time 179 ± 65 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
30 Aug 2026PR01
Import / long-lead
2Rp 228.0M26 Nov 2027
open
453 d
14 Nov 2025PR03
Regular replenishment
1Rp 228.6M15 Mar 2026121 d
30 Jun 2025PR06
Regular replenishment
2Rp 232.4M21 May 2026325 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
06 Sept 2026MediumPX_KC-308BInstall scaffolding at KC-308B
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
04 Jun 2026HighPX_KC-308BRepair insulation KC-308B
24 May 2026HighPX_KT-383AKT-383A steam leak at gland
08 May 2026MediumPX_KC-308B[MSI-B-26-PPX-327] Permanent repair

Recent goods issues

Never issued in the 17-month history.