SEAL,LABYRINTH,TYPE BG775,A182F11
Material 4100084751 · SEAL · Plant 1000
ALong-leadMaintainInsurance gap
- Material
- 4100084751
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 4 FuncLocs A/B)
- Supplier
- DUTA SEJAHTERA ABADI PT
- Lead time
- 179 d · P80 213 d
- Unit price
- Rp 228.6M
Recommendation
- 1.Forecast 0.5 SET/year: 0.5 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~179 days; expected demand during lead time 0.2.
- 3.A 97.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 26 Nov 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
97.7%
stockout risk now 0%
Unit price
Rp 228.6M
PO history
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 713.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 4 functional locations
2 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-308B REFLUX BLOWER | A | 1 | 6 | 2.28 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-383A TURBINE FOR KC-383A | S | 3 | 7 | 3.67 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
Lead time and procurement
Lead time 179 ± 65 days (PO history + category, 2 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 Aug 2026 | PR01 Import / long-lead | 2 | Rp 228.0M | 26 Nov 2027 open | 453 d |
| 14 Nov 2025 | PR03 Regular replenishment | 1 | Rp 228.6M | 15 Mar 2026 | 121 d |
| 30 Jun 2025 | PR06 Regular replenishment | 2 | Rp 232.4M | 21 May 2026 | 325 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 06 Sept 2026 | Medium | PX_KC-308B | Install scaffolding at KC-308B |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 04 Jun 2026 | High | PX_KC-308B | Repair insulation KC-308B |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 08 May 2026 | Medium | PX_KC-308B | [MSI-B-26-PPX-327] Permanent repair |
Recent goods issues
Never issued in the 17-month history.