SEAL,LABYRINTH,MODEL NH642,CS

Material 4100084857 · SEAL · Plant 1000

SReduceNon-moving
Material
4100084857
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
S (0 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 0.9 SET/year: 0.2 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 0.1.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 1 exceeds the level to keep (0) by 1.
Convert to Non StockPrice estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 631,540/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.05% for ~71 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-582B
CAUSTIC BLOWER
S1103.57
PX_KC-505D
METHANE COMPRESSOR
S111.00

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
07 Jul 2027PX_KC-505DCompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026HighPX_KC-582BKC-582B high vibration
26 Aug 2026LowPX_KC-582BPainting KC-582B
08 Jul 2026LowPX_KC-582BInstall scaffolding at KC-582B
28 Apr 2026HighPX_KC-582BKC-582B lube oil filter DP high
20 Apr 2026EmergencyPX_KC-582BRepair insulation KC-582B
05 Nov 2025MediumPX_KC-582BReplace lamp as per PM finding
15 Oct 2025MediumPX_KC-582BOverhaul
03 Oct 2025MediumPX_KC-582BKC-582B lube oil filter DP high
26 Sept 2025MediumPX_KC-582BKC-582B lube oil filter DP high
21 Jun 2025HighPX_KC-505DRepair insulation KC-505D

Recent goods issues

Never issued in the 17-month history.