Sparely
DU

SEAL,LABYRINTH,SIZE ZM706,A105

Material 4100085266 · SEAL · Plant 1000

AReduceNon-moving
Material
4100085266
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 1.0 SET/year: 0.3 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 0.8 (incl. 0.7 planned).
  • 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 20 exceeds the level to keep (3) by 17.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
20 / 0
no open PO
Today Min / Max
10 / 23
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.2%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 487.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-867D
CONDENSATE FAN
A162.71
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Sept 2026MediumPX_KC-867DLeak from packing
11 Jul 2026MediumPX_KC-867DKC-867D bearing temp high
11 Jun 2026LowPX_KT-264ALeak from packing
03 Jun 2026LowPX_KC-867DLeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KC-867DInspect coupling KC-867D
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A

Recent goods issues

Never issued in the 17-month history.

Sparely