SEAL,LABYRINTH,SIZE ZM706,A105
Material 4100085266 · SEAL · Plant 1000
AReduceNon-moving
- Material
- 4100085266
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (2 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 94.6M (est.)
Recommendation
- 1.Forecast 1.0 SET/year: 0.3 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~150 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Stock 20 exceeds the level to keep (3) by 17.
- 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
20 / 0
no open PO
Today Min / Max
10 / 23
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.2%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 487.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-867D CONDENSATE FAN | A | 1 | 6 | 2.71 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-264A TURBINE FOR KC-264A | S | 1 | 4 | 2.39 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 17 Sept 2026 | Medium | PX_KC-867D | Leak from packing |
| 11 Jul 2026 | Medium | PX_KC-867D | KC-867D bearing temp high |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 03 Jun 2026 | Low | PX_KC-867D | Leak from packing |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 20 Nov 2025 | Medium | PX_KC-867D | Inspect coupling KC-867D |
| 20 Nov 2025 | Medium | PX_KT-419A | Leak from packing |
| 10 Nov 2025 | Medium | PX_KT-419A | Painting KT-419A |
Recent goods issues
Never issued in the 17-month history.