SEAL,LABYRINTH,MODEL RO752,NBR
Material 4100085397 · SEAL · Plant 1000
AReduceExcess
- Material
- 4100085397
- Category
- SEAL
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- RAJAWALI REFRAKTORI PRATAMA PT
- Lead time
- 150 d · P80 213 d
- Unit price
- Rp 164.4M
Recommendation
- 1.Forecast 1.6 SET/year: 1.6 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~150 days; expected demand during lead time 0.7.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
- 4.Stock 6 exceeds the level to keep (4) by 2.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Single sourceOpen POLead time estimated
On hand / on order
6 / 5
next delivery 13 Jan 2028
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
4
order qty 1
Service level
99.5%
stockout risk now 0%
Unit price
Rp 164.4M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 174 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KC-886D BOTTOM FAN | B | 1 | 4 | 1.43 |
Lead time and procurement
Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Aug 2026 | PR03 Regular replenishment | 2 | Rp 164.4M | 09 Oct 2028 open | 789 d |
| 20 Mar 2026 | PR03 Regular replenishment | 1 | Rp 171.0M | 25 Apr 2028 open | 767 d |
| 06 Oct 2025 | PR01 Import / long-lead | 2 | Rp 164.1M | 13 Jan 2028 open | 829 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Low | PX_KC-886D | KC-886D high vibration |
| 10 Jul 2026 | Medium | PX_KC-886D | Install scaffolding at KC-886D |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 20 Apr 2026 | Low | PX_KC-886D | Replace lamp as per PM finding |
| 02 Apr 2026 | Medium | PX_KT-397A | Follow up after steam upset KT-397A |
| 10 May 2025 | Medium | PX_KT-397A | Leak from packing |
| 04 May 2025 | Medium | PX_KC-886D | [MSI-B-25-PZW-222/M] Replace line |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Apr 2026 | 1 | 201000014233 | Corrective |
| 09 Jan 2026 | 1 | 201000019857 | Corrective |