FILTER ELEMENT,SEAL GAS,5MICRON,P/N FE-9

Material 4100086104 · FILTER ELEMENT · Plant 1000

ALong-leadReduceExcess
Material
4100086104
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (23 of 39 FuncLocs A/B)
Supplier
MEGA UTAMA GLOBAL PT
Lead time
128 d · P80 171 d
Unit price
Rp 4.8M

Recommendation

  • 1.Forecast 163 EA/year: 147 unplanned (recency-weighted compound poisson (own history)) + 16 from the maintenance plan.
  • 2.Lead time ~128 days; expected demand during lead time 58 (incl. 6.4 planned).
  • 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 140, order up to 163.
  • 4.Stock 507 exceeds the level to keep (163) by 344.
  • 5.Long lead time: 80% of deliveries took up to 171 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 39 FuncLoc(s), 23 of them criticality A/B.
  • 7.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 23Single sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
507 / 730
next delivery 10 Oct 2026
Today Min / Max
10 / 25
static parameters in BoM
Rec. Min (reorder point)
140
safety stock 83
Rec. Max
163
order qty 23
Service level
99.5%
stockout risk now 0%
Unit price
Rp 4.8M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 36 issue days in the last 180 days, last issue 8 days ago, 36 failure notifications on its equipment in 90 days, 5 planned jobs in 90 days, 16 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (33 units) excluded from the baseline.

Demand pattern Smooth · 150 issue days · 9 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 44.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 39 functional locations

23 with criticality A/B · 44 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-452
HYDROGEN FAN
A162.71
PX_KC-867D
CONDENSATE FAN
A162.71
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-447
LUBE OIL COMPRESSOR
A141.85
PX_KC-752A
CONDENSATE BLOWER
A141.85
PX_KC-396
WASH WATER BLOWER
A131.43
PX_KC-671D
FEED BLOWER
A131.00
PX_KC-137A
C4 PRODUCT COMPRESSOR
A121.43
PX_KC-801
DEMIN WATER FAN
A121.43

Lead time and procurement

Lead time 128 ± 75 days (PO history, 37 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
22 Sept 2026PR06
Regular replenishment
58Rp 4.8M02 Nov 2026
open
41 d
06 Sept 2026PR03
Regular replenishment
52Rp 4.9M27 Jan 2027
open
143 d
05 Aug 2026PR04
Regular (other)
132Rp 4.7M07 Apr 2027
open
245 d
27 Jul 2026PR05
Project / turnaround
71Rp 4.9M02 Oct 2027
open
432 d
15 Jul 2026PR06
Regular replenishment
72Rp 5.0M08 Sept 202655 d
28 Jun 2026PR03
Regular replenishment
107Rp 4.8M22 Aug 202655 d
26 Jun 2026PR03
Regular replenishment
80Rp 4.8M13 Jun 2027
open
352 d
11 Jun 2026PR03
Regular replenishment
140Rp 4.9M25 Oct 2026
open
136 d
26 May 2026PR03
Regular replenishment
140Rp 5.0M10 Oct 2026
open
137 d
22 May 2026PR03
Regular replenishment
48Rp 4.7M31 Jul 202670 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
04 Oct 2026PX_KC-830DFilter element replacement0.72
06 Oct 2026PX_KC-752AFilter element replacement0.72
05 Nov 2026PX_KC-264AFilter element replacement0.72
01 Dec 2026PX_KC-452Filter element replacement0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
01 Jan 2027PX_KC-479CFilter element replacement0.72
13 Jan 2027PX_KC-538Filter element replacement1.43
31 Jan 2027PX_KC-137AFilter element replacement0.72
07 Feb 2027PX_KC-618BFilter element replacement0.72
03 Mar 2027PX_KC-621Filter element replacement1.43
07 Apr 2027PX_KC-752AFilter element replacement0.72
02 Jun 2027PX_KC-452Filter element replacement0.72
25 Jun 2027PX_KC-663AFilter element replacement0.72
03 Jul 2027PX_KC-479CFilter element replacement0.72
15 Jul 2027PX_KC-538Filter element replacement1.43
02 Aug 2027PX_KC-137AFilter element replacement0.72
02 Sept 2027PX_KC-621Filter element replacement1.43
05 Sept 2027PX_KC-830DFilter element replacement0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026LowPX_KC-886DKC-886D high vibration
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
24 Sept 2026EmergencyPX_KC-538KC-538 high vibration
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
23 Sept 2026MediumPX_KC-513KC-513 high vibration
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
17 Sept 2026MediumPX_KC-867DLeak from packing
16 Sept 2026EmergencyPX_KC-538Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
23 Sept 20261209000029477Other maintenance
20 Sept 20261201000010618Corrective
18 Sept 20261201000026093Corrective
15 Sept 20261201000001079Corrective
14 Sept 20262201000001040Corrective
14 Sept 20261204000029260Preventive
13 Sept 20261204000000772Preventive
11 Sept 20261201000020312Corrective
02 Sept 20261201000023287Corrective
24 Aug 20261201000000994Corrective
16 Aug 20261204000039855Preventive
10 Aug 20263201000006061Corrective
08 Aug 20261201000028952Corrective
06 Aug 20261201000005043Corrective
04 Aug 20262201000010969Corrective