Sparely
DU

FILTER ELEMENT,SEAL GAS,25MICRON,P/N FE-

Material 4100086180 · FILTER ELEMENT · Plant 1000

AReduceExcess
Material
4100086180
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (9 of 17 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
60 d · P80 82 d
Unit price
Rp 750,164

Recommendation

  • 1.Forecast 44 EA/year: 39 unplanned (recency-weighted compound poisson (own history)) + 4.3 from the maintenance plan.
  • 2.Lead time ~60 days; expected demand during lead time 7.1 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 23, order up to 53.
  • 4.Stock 2,260 exceeds the level to keep (53) by 2,207.
  • 5.Installed on 17 FuncLoc(s), 9 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 5Single sourceOpen POPlanned demand in lead timeSame description as 1 other material number
On hand / on order
2,260 / 39
next delivery 31 Oct 2026
Today Min / Max
22 / 63
static parameters in BoM
Rec. Min (reorder point)
23
safety stock 16
Rec. Max
53
order qty 30
Service level
99.9%
stockout risk now 0%
Unit price
Rp 750,164
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 10 issue days in the last 180 days, last issue 4 days ago, 20 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 7 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (9 units) excluded from the baseline.

Demand pattern Erratic · 39 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 12.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 17 functional locations

9 with criticality A/B · 17 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_KC-419A
PROPYLENE FAN
A1195.71
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-452
HYDROGEN FAN
A162.71
PX_KC-752A
CONDENSATE BLOWER
A141.85
PX_KC-396
WASH WATER BLOWER
A131.43
PX_KC-588
CAUSTIC FAN
A121.00
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_KC-618B
WASH WATER BLOWER
A100.57
PX_KC-371B
BOTTOM FAN
B100.57
PX_KC-843
FUEL OIL COMPRESSOR
S1218.28
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KC-422A
C4 PRODUCT BLOWER
S162.71

Lead time and procurement

Lead time 60 ± 32 days (PO history, 21 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
21 Sept 2026PR03
Regular replenishment
12Rp 722,74820 Nov 2026
open
60 d
01 Sept 2026PR04
Regular (other)
27Rp 770,86231 Oct 2026
open
60 d
07 Aug 2026PR03
Regular replenishment
30Rp 782,04322 Sept 202646 d
24 Jun 2026PR06
Regular replenishment
32Rp 732,07825 Aug 202662 d
31 May 2026PR03
Regular replenishment
15Rp 754,57711 Jul 202641 d
10 May 2026PR03
Regular replenishment
23Rp 760,67205 Jun 202626 d
10 May 2026PR03
Regular replenishment
16Rp 720,98531 Jul 202682 d
02 Apr 2026PR06
Regular replenishment
24Rp 780,42414 May 202642 d
27 Mar 2026PR06
Regular replenishment
19Rp 743,38109 May 202643 d
16 Mar 2026PR06
Regular replenishment
16Rp 768,39208 May 202653 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
06 Oct 2026PX_KC-752AFilter element replacement0.72
01 Dec 2026PX_KC-452Filter element replacement0.72
07 Feb 2027PX_KC-618BFilter element replacement0.72
07 Apr 2027PX_KC-752AFilter element replacement0.72
02 Jun 2027PX_KC-452Filter element replacement0.72
07 Jul 2027PX_KC-505DCompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Sept 2026HighPY_KC-419AOverhaul
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
23 Sept 2026MediumPY_KC-419AInspect coupling KC-419A
21 Sept 2026MediumPX_KC-843Painting KC-843
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
18 Sept 2026MediumPY_KC-419AInstall scaffolding at KC-419A
16 Sept 2026LowPX_KC-843Inspect coupling KC-843
05 Sept 2026MediumPX_KC-452Overhaul
05 Sept 2026MediumPX_KC-452Inspect coupling KC-452
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 20261201000030463Corrective
23 Sept 20261201000037585Corrective
23 Jul 20262201000026095Corrective
22 Jul 20261201000021281Corrective
20 Jul 20261201000008147Corrective
20 Jul 20261201000028005Corrective
19 Jul 20261201000008147Corrective
30 Jun 20261201000006253Corrective
27 Jun 20262201000036525Corrective
23 Apr 20261201000015111Corrective
09 Apr 20261205000036152Other maintenance
27 Feb 20261201000026488Corrective
19 Feb 20261204000036808Preventive
11 Feb 20261201000037687Corrective
22 Jan 20261201000012637Corrective