FILTER ELEMENT,FUEL GAS,5MICRON,P/N FE-8
Material 4100086264 · FILTER ELEMENT · Plant 1000
ALong-leadReduceExcess
- Material
- 4100086264
- Category
- FILTER ELEMENT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 9 FuncLocs A/B)
- Supplier
- DUTA TEKNOLOGI ABADI PT
- Lead time
- 75 d · P80 110 d
- Unit price
- Rp 1.2M
Recommendation
- 1.Forecast 18 EA/year: 14 unplanned (recency-weighted compound poisson (own history)) + 4.3 from the maintenance plan.
- 2.Lead time ~75 days; expected demand during lead time 5.0 (incl. 2.1 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 28.
- 4.Stock 281 exceeds the level to keep (28) by 253.
- 5.Long lead time: 80% of deliveries took up to 110 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 9 FuncLoc(s), 5 of them criticality A/B.
- 7.ML early warning: 91% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 5Single sourcePlanned demand in lead time
On hand / on order
281 / 0
no open PO
Today Min / Max
5 / 14
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 7
Rec. Max
28
order qty 16
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.2M
PO history
ML early warning: 91% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 1 days ago, 6 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (7 units) excluded from the baseline.
Demand pattern Intermittent · 20 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.
Installed on 9 functional locations
5 with criticality A/B · 14 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-460B TURBINE FOR KC-460B | A | 4 | 2 | 1.96 |
| PY_KC-636C SLOP OIL COMPRESSOR | A | 1 | 1 | 0.57 |
| PX_KC-669 DEMIN WATER BLOWER | A | 3 | 0 | 0.57 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 75 ± 31 days (PO history, 4 PO lines) · on-time 60%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Apr 2026 | PR03 Regular replenishment | 8 | Rp 1.2M | 07 Jul 2026 | 86 d |
| 19 Feb 2026 | PR06 Regular replenishment | 15 | Rp 1.2M | 23 Apr 2026 | 63 d |
| 14 Jan 2026 | PR03 Regular replenishment | 10 | Rp 1.2M | 24 Apr 2026 | 100 d |
| 24 Jun 2025 | PR03 Regular replenishment | 7 | Rp 1.2M | 26 Oct 2025 | 124 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Oct 2026 | PX_KC-669 | Filter element replacement | 2.15 |
| 02 Apr 2027 | PX_KC-669 | Filter element replacement | 2.15 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Sept 2026 | 1 | 201000020250 | Corrective |
| 04 Sept 2026 | 1 | 203000008243 | Turnaround |
| 03 Sept 2026 | 1 | 203000008243 | Turnaround |
| 31 Jul 2026 | 1 | 204000016683 | Preventive |
| 19 Jul 2026 | 2 | 201000028005 | Corrective |
| 25 May 2026 | 1 | 201000019630 | Corrective |
| 08 Feb 2026 | 1 | 201000001822 | Corrective |
| 25 Jan 2026 | 2 | 201000039852 | Corrective |
| 19 Jan 2026 | 1 | 201000023909 | Corrective |
| 13 Jan 2026 | 1 | 201000021923 | Corrective |
| 01 Jan 2026 | 1 | 201000036151 | Corrective |
| 30 Dec 2025 | 1 | 201000036693 | Corrective |
| 27 Dec 2025 | 1 | 201000027268 | Corrective |
| 26 Dec 2025 | 2 | 203000006078 | Turnaround |
| 24 Dec 2025 | 1 | 201000022133 | Corrective |