FILTER ELEMENT,SEAL GAS,3MICRON,P/N FE-2
Material 4100086272 · FILTER ELEMENT · Plant 1000
ALong-leadMonitorHealthy
- Material
- 4100086272
- Category
- FILTER ELEMENT
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 8 FuncLocs A/B)
- Supplier
- SAMUDRA TEKNOLOGI INTERNASIONAL PT
- Lead time
- 78 d · P80 102 d
- Unit price
- Rp 7.5M
Recommendation
- 1.Forecast 16 EA/year: 15 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 2.Lead time ~78 days; expected demand during lead time 3.2.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 18.
- 4.Long lead time: 80% of deliveries took up to 102 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 8 FuncLoc(s), 4 of them criticality A/B.
- 6.ML early warning: 81% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 3Single source
On hand / on order
13 / 0
no open PO
Today Min / Max
7 / 16
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 9
Rec. Max
18
order qty 6
Service level
100.0%
stockout risk now 0%
Unit price
Rp 7.5M
PO history
ML early warning: 81% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 68 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (4 units) excluded from the baseline.
Demand pattern Lumpy · 18 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.
Installed on 8 functional locations
4 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KC-527 METHANOL BLOWER | A | 1 | 0 | 0.57 |
| PX_KC-225D INHIBITOR COMPRESSOR | B | 1 | 9 | 2.71 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_KC-422A C4 PRODUCT BLOWER | S | 2 | 6 | 2.71 |
| PX_KC-150A HYDROGEN FAN | S | 1 | 2 | 1.00 |
| PX_KC-890A INHIBITOR FAN | S | 1 | 2 | 1.00 |
Lead time and procurement
Lead time 78 ± 55 days (PO history, 7 PO lines) · on-time 25%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Jul 2026 | PR03 Regular replenishment | 10 | Rp 7.7M | 02 Sept 2026 | 53 d |
| 26 Jun 2026 | PR06 Regular replenishment | 7 | Rp 7.4M | 24 Aug 2026 | 59 d |
| 02 Mar 2026 | PR04 Regular (other) | 7 | Rp 7.2M | 22 May 2026 | 81 d |
| 06 Jan 2026 | PR01 Import / long-lead | 4 | Rp 7.5M | 14 Aug 2026 | 220 d |
| 25 Sept 2025 | PR06 Regular replenishment | 11 | Rp 7.7M | 29 Nov 2025 | 65 d |
| 06 Aug 2025 | PR03 Regular replenishment | 10 | Rp 7.1M | 21 Nov 2025 | 107 d |
| 23 May 2025 | PR06 Regular replenishment | 9 | Rp 7.5M | 29 Jun 2025 | 37 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 04 Mar 2027 | PX_KC-150A | Filter element replacement | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 11 Sept 2026 | Low | PX_KC-225D | KC-225D lube oil filter DP high |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 22 Aug 2026 | Low | PX_KC-225D | Install scaffolding at KC-225D |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 27 Jul 2026 | Low | PX_KC-225D | Painting KC-225D |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 08 Jul 2026 | Medium | PX_KC-422A | KC-422A high vibration |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Jul 2026 | 1 | 201000018238 | Corrective |
| 24 Jul 2026 | 1 | 204000026843 | Preventive |
| 19 Apr 2026 | 1 | 201000028316 | Corrective |
| 02 Apr 2026 | 2 | 201000012873 | Corrective |
| 01 Apr 2026 | 2 | 201000012873 | Corrective |
| 06 Feb 2026 | 2 | 201000023754 | Corrective |
| 28 Jan 2026 | 1 | 201000016979 | Corrective |
| 27 Jan 2026 | 1 | 203000033471 | Turnaround |
| 11 Jan 2026 | 1 | 201000008824 | Corrective |
| 31 Dec 2025 | 3 | 201000020705 | Corrective |
| 26 Dec 2025 | 2 | 201000036852 | Corrective |
| 25 Dec 2025 | 1 | 201000033440 | Corrective |
| 14 Dec 2025 | 1 | 201000019641 | Corrective |
| 04 Dec 2025 | 1 | 201000009221 | Corrective |
| 28 Nov 2025 | 1 | 203000032713 | Turnaround |