FILTER ELEMENT,LUBE OIL,25MICRON,P/N FE-
Material 4100086306 · FILTER ELEMENT · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100086306
- Category
- FILTER ELEMENT
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (6 of 9 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 93 d · P80 133 d
- Unit price
- Rp 770,336
Recommendation
- 1.Forecast 14 EA/year: 13 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
- 2.Lead time ~93 days; expected demand during lead time 4.7 (incl. 1.4 planned).
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 14, order up to 29.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 29 now.
- 5.Long lead time: 80% of deliveries took up to 133 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 9 FuncLoc(s), 6 of them criticality A/B.
- 7.ML early warning: 83% probability of demand in the next 90 days.
- 8.Identical part 4100087655 holds spare stock: transfer 19 EA instead of buying, then buy the remaining 10.
Proposed purchase requisition
10 EA
Rp 7.7M · order by 01 Oct 2026
Expected arrival ≈ 93 days
Long-leadML early warningConvert to Stock ItemLast turnaround used 5Single sourcePlanned demand in lead timeSame description as 1 other material number
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
14
safety stock 10
Rec. Max
29
order qty 15
Service level
100.0%
stockout risk now 100%
Unit price
Rp 770,336
PO history
ML early warning: 83% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 21 days ago, 6 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (6 units) excluded from the baseline.
Demand pattern Intermittent · 12 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.
Installed on 9 functional locations
6 with criticality A/B · 13 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-460B TURBINE FOR KC-460B | A | 1 | 2 | 1.96 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_KC-397A DILUTION STEAM FAN | A | 4 | 1 | 0.57 |
| PX_KC-178A QUENCH OIL FAN | A | 1 | 0 | 0.57 |
| PX_KC-527 METHANOL BLOWER | A | 1 | 0 | 0.57 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KC-365C INHIBITOR BLOWER | S | 1 | 7 | 3.14 |
| PX_KT-383A TURBINE FOR KC-383A | S | 2 | 7 | 3.67 |
| PX_KT-264A TURBINE FOR KC-264A | S | 1 | 4 | 2.39 |
Lead time and procurement
Lead time 93 ± 33 days (PO history, 7 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 May 2026 | PR10 Other | 4 | Rp 770,336 | 02 Sept 2026 | 111 d |
| 13 Apr 2026 | PR04 Regular (other) | 8 | Rp 740,688 | 10 Jul 2026 | 88 d |
| 19 Mar 2026 | PR03 Regular replenishment | 3 | Rp 785,333 | 05 Aug 2026 | 139 d |
| 15 Feb 2026 | PR06 Regular replenishment | 3 | Rp 783,708 | 29 Jul 2026 | 164 d |
| 16 Jan 2026 | PR06 Regular replenishment | 9 | Rp 742,363 | 16 Apr 2026 | 90 d |
| 10 Sept 2025 | PR01 Import / long-lead | 10 | Rp 751,831 | 18 Dec 2025 | 99 d |
| 07 Jul 2025 | PR06 Regular replenishment | 8 | Rp 773,148 | 27 Sept 2025 | 82 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 05 Nov 2026 | PX_KC-178A | Filter element replacement | 0.72 |
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_KC-365C | KC-365C lube oil filter DP high |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 26 Jul 2026 | Medium | PX_KC-365C | Inspect coupling KC-365C |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Sept 2026 | 2 | 201000038057 | Corrective |
| 15 Aug 2026 | 1 | 201000032640 | Corrective |
| 30 Jun 2026 | 2 | 209000022177 | Other maintenance |
| 04 Apr 2026 | 2 | 201000009302 | Corrective |
| 09 Mar 2026 | 1 | 203000020244 | Turnaround |
| 11 Feb 2026 | 1 | 201000015484 | Corrective |
| 03 Feb 2026 | 1 | 201000016884 | Corrective |
| 10 Jan 2026 | 1 | 201000001471 | Corrective |
| 09 Jan 2026 | 1 | 201000031110 | Corrective |
| 05 Jan 2026 | 1 | 201000016989 | Corrective |
| 22 Dec 2025 | 1 | 203000001878 | Turnaround |
| 14 Nov 2025 | 1 | 203000035490 | Turnaround |
| 11 Nov 2025 | 2 | 203000039046 | Turnaround |
| 05 Nov 2025 | 1 | 203000039255 | Turnaround |
| 19 Sept 2025 | 2 | 201000010957 | Corrective |