Sparely
DU

FILTER ELEMENT,LUBE OIL,25MICRON,P/N FE-

Material 4100086306 · FILTER ELEMENT · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100086306
Category
FILTER ELEMENT
Base unit
EA
MRP type
Non Stock
Criticality
A (6 of 9 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
93 d · P80 133 d
Unit price
Rp 770,336

Recommendation

  • 1.Forecast 14 EA/year: 13 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 2.Lead time ~93 days; expected demand during lead time 4.7 (incl. 1.4 planned).
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 14, order up to 29.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 29 now.
  • 5.Long lead time: 80% of deliveries took up to 133 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 9 FuncLoc(s), 6 of them criticality A/B.
  • 7.ML early warning: 83% probability of demand in the next 90 days.
  • 8.Identical part 4100087655 holds spare stock: transfer 19 EA instead of buying, then buy the remaining 10.
Proposed purchase requisition
10 EA
Rp 7.7M · order by 01 Oct 2026
Expected arrival ≈ 93 days
Long-leadML early warningConvert to Stock ItemLast turnaround used 5Single sourcePlanned demand in lead timeSame description as 1 other material number
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
14
safety stock 10
Rec. Max
29
order qty 15
Service level
100.0%
stockout risk now 100%
Unit price
Rp 770,336
PO history
ML early warning: 83% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 21 days ago, 6 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (6 units) excluded from the baseline.

Demand pattern Intermittent · 12 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 9 functional locations

6 with criticality A/B · 13 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_KC-397A
DILUTION STEAM FAN
A410.57
PX_KC-178A
QUENCH OIL FAN
A100.57
PX_KC-527
METHANOL BLOWER
A100.57
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KC-365C
INHIBITOR BLOWER
S173.14
PX_KT-383A
TURBINE FOR KC-383A
S273.67
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 93 ± 33 days (PO history, 7 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
14 May 2026PR10
Other
4Rp 770,33602 Sept 2026111 d
13 Apr 2026PR04
Regular (other)
8Rp 740,68810 Jul 202688 d
19 Mar 2026PR03
Regular replenishment
3Rp 785,33305 Aug 2026139 d
15 Feb 2026PR06
Regular replenishment
3Rp 783,70829 Jul 2026164 d
16 Jan 2026PR06
Regular replenishment
9Rp 742,36316 Apr 202690 d
10 Sept 2025PR01
Import / long-lead
10Rp 751,83118 Dec 202599 d
07 Jul 2025PR06
Regular replenishment
8Rp 773,14827 Sept 202582 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
05 Nov 2026PX_KC-178AFilter element replacement0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
26 Jul 2026MediumPX_KC-365CInspect coupling KC-365C
11 Jun 2026LowPX_KT-264ALeak from packing
24 May 2026HighPX_KT-383AKT-383A steam leak at gland
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A

Recent goods issues

Posting dateQtyOrderOrder type
10 Sept 20262201000038057Corrective
15 Aug 20261201000032640Corrective
30 Jun 20262209000022177Other maintenance
04 Apr 20262201000009302Corrective
09 Mar 20261203000020244Turnaround
11 Feb 20261201000015484Corrective
03 Feb 20261201000016884Corrective
10 Jan 20261201000001471Corrective
09 Jan 20261201000031110Corrective
05 Jan 20261201000016989Corrective
22 Dec 20251203000001878Turnaround
14 Nov 20251203000035490Turnaround
11 Nov 20252203000039046Turnaround
05 Nov 20251203000039255Turnaround
19 Sept 20252201000010957Corrective