Sparely
DU

FILTER ELEMENT,FUEL GAS,5MICRON,P/N FE-7

Material 4100086420 · FILTER ELEMENT · Plant 1000

ALong-leadMonitorHealthy
Material
4100086420
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 6 FuncLocs A/B)
Supplier
EUROSEAL TECHNIK GMBH
Lead time
97 d · P80 201 d
Unit price
Rp 669,945

Recommendation

  • 1.Forecast 3.8 EA/year: 3.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~97 days; expected demand during lead time 1.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 9.
  • 4.Long lead time: 80% of deliveries took up to 201 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
  • 6.ML early warning: 40% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 2Single sourceOpen PO
On hand / on order
2 / 4
next delivery 23 Oct 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
9
order qty 4
Service level
99.9%
stockout risk now 0%
Unit price
Rp 669,945
PO history
ML early warning: 40% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 169 days ago, 15 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (3 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 6 functional locations

4 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_KC-435A
FUEL OIL AIR COMPRESSOR
A121.00
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KC-843
FUEL OIL COMPRESSOR
S1218.28
PX_KT-383A
TURBINE FOR KC-383A
S173.67

Lead time and procurement

Lead time 97 ± 68 days (PO history, 3 PO lines) · on-time 27%

PR dateTypeQtyUnit priceDeliveryLead time
07 Sept 2026PR03
Regular replenishment
4Rp 669,94523 Oct 2026
open
46 d
13 Nov 2025PR04
Regular (other)
2Rp 682,86602 Apr 2026140 d
27 Oct 2025PR01
Import / long-lead
2Rp 653,30726 Jun 2026242 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026LowPX_KC-717Leak from packing
21 Sept 2026MediumPX_KC-843Painting KC-843
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026LowPX_KC-843Inspect coupling KC-843
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
29 Aug 2026MediumPX_KC-843Replace lamp as per PM finding
26 Aug 2026MediumPX_KC-843[MSI-B-26-RLH-211] Permanent repair
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A

Recent goods issues

Posting dateQtyOrderOrder type
15 Apr 20261201000020916Corrective
19 Nov 20252203000020131Turnaround
25 Aug 20251201000039654Corrective
24 Jun 20251203000034428Turnaround
02 Jun 20251201000002694Corrective
20 May 20251201000015314Corrective
09 May 20251201000030975Corrective