Sparely
DU

FILTER ELEMENT,SEAL GAS,5MICRON,P/N FE-6

Material 4100086531 · FILTER ELEMENT · Plant 1000

AReduceNon-moving
Material
4100086531
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
51 d · P80 100 d
Unit price
Rp 2.8M (est.)

Recommendation

  • 1.Forecast 3.6 EA/year: 0.7 unplanned (installed-base failure prior (no history)) + 2.9 from the maintenance plan.
  • 2.Lead time ~51 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 7.
  • 4.Stock 11 exceeds the level to keep (7) by 4.
  • 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimatedSame description as 1 other material number
On hand / on order
11 / 0
no open PO
Today Min / Max
4 / 13
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
7
order qty 4
Service level
100.0%
stockout risk now 0%
Unit price
Rp 2.8M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 5 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 268.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 5 functional locations

3 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A372.81
PX_KC-279C
C3 RECYCLE COMPRESSOR
A131.43
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-264A
TURBINE FOR KC-264A
S242.39

Lead time and procurement

Lead time 51 ± 39 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul1.43
21 Jan 2027PX_KC-279CFilter element replacement0.72
23 Jul 2027PX_KC-279CFilter element replacement0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
05 Sept 2026MediumPX_KC-279COverhaul
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
03 Jul 2026MediumPX_KC-279CInspect coupling KC-279C
11 Jun 2026LowPX_KT-264ALeak from packing
13 May 2026LowPX_KT-447KT-447 trip test
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing

Recent goods issues

Never issued in the 17-month history.