Sparely
DU

FILTER ELEMENT,FUEL GAS,3MICRON,P/N FE-2

Material 4100086841 · FILTER ELEMENT · Plant 1000

ALong-leadTransferNormalSlow-moving
Material
4100086841
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
GEMILANG SUPLINDO SENTOSA PT
Lead time
57 d · P80 100 d
Unit price
Rp 5.3M

Recommendation

  • 1.Forecast 2.2 EA/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~57 days; expected demand during lead time 0.3.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
  • 4.On hand 1 + on order 0 is at or below the reorder point: 5 needed.
  • 5.Long lead time: 80% of deliveries took up to 100 days and the fastest seen in its category 22 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
  • 7.Identical part 4100087476 holds spare stock: transfer 5 EA instead of buying — no purchase needed.
Long-leadSingle sourceSame description as 1 other material number
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
100.0%
stockout risk now 5%
Unit price
Rp 5.3M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 262 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 3 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_KC-879A
CONDENSATE FAN
S462.71

Lead time and procurement

Lead time 57 ± 39 days (PO history + category, 1 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
02 Feb 2026PR05
Project / turnaround
1Rp 5.3M16 Apr 202673 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
07 Sept 2026MediumPX_KC-879AReplace lamp as per PM finding
10 Jun 2026MediumPX_KC-879A[MSI-B-26-PWM-186/M] Replace line
15 May 2026MediumPX_KC-879AOverhaul
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
05 Jan 2026HighPX_KC-879AReplace lamp as per PM finding
04 Jan 2026MediumPX_KT-513KT-513 governor valve hunting
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A

Recent goods issues

Posting dateQtyOrderOrder type
12 Jan 20261201000015803Corrective
Sparely