FILTER ELEMENT,SEAL GAS,3MICRON,P/N FE-5

Material 4100086893 · FILTER ELEMENT · Plant 1000

AReduceNon-moving
Material
4100086893
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
51 d · P80 100 d
Unit price
Rp 2.8M (est.)

Recommendation

  • 1.Forecast 1.8 EA/year: 0.3 unplanned (installed-base failure prior (no history)) + 1.4 from the maintenance plan.
  • 2.Lead time ~51 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.Stock 17 exceeds the level to keep (4) by 13.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
17 / 0
no open PO
Today Min / Max
4 / 11
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 2.8M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 117.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-464A
CONDENSATE BLOWER
A121.43
PX_KT-383A
TURBINE FOR KC-383A
S173.67
PX_KC-505D
METHANE COMPRESSOR
S111.00

Lead time and procurement

Lead time 51 ± 39 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
03 Feb 2027PX_KC-464AFilter element replacement0.72
07 Jul 2027PX_KC-505DCompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
24 May 2026HighPX_KT-383AKT-383A steam leak at gland
02 Oct 2025MediumPX_KC-464AKC-464A lube oil filter DP high
25 Jul 2025MediumPX_KC-464AKC-464A lube oil filter DP high
23 Jun 2025MediumPX_KT-383AKT-383A governor valve hunting
21 Jun 2025HighPX_KC-505DRepair insulation KC-505D

Recent goods issues

Never issued in the 17-month history.