Sparely
DU

FILTER ELEMENT,LUBE OIL,3MICRON,P/N FE-2

Material 4100086953 · FILTER ELEMENT · Plant 1000

AReorderCriticalStockout
Material
4100086953
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
51 d · P80 100 d
Unit price
Rp 2.8M (est.)

Recommendation

  • 1.Forecast 1.0 EA/year: 0.3 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~51 days; expected demand during lead time 0.0.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 11.1M · order by 01 Oct 2026
Expected arrival ≈ 51 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
99.9%
stockout risk now 3%
Unit price
Rp 2.8M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 112.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_KC-222B
LEAN AMINE COMPRESSOR
A151.85

Lead time and procurement

Lead time 51 ± 39 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
20 Aug 2027PX_KC-222BFilter element replacement0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026LowPX_KC-717Leak from packing
08 Aug 2026MediumPX_KC-717Repair insulation KC-717
20 Jul 2026LowPX_KC-717Inspect coupling KC-717
05 Jul 2026MediumPX_KC-717Overhaul
02 Jul 2026HighPX_KC-222BReplace lamp as per PM finding
12 Mar 2026LowPX_KC-717Replace lamp as per PM finding
01 Mar 2026MediumPX_KC-717Leak from packing
05 Feb 2026MediumPX_KC-222BInstall scaffolding at KC-222B
01 Jan 2026LowPX_KC-222BKC-222B high vibration
16 Nov 2025MediumPX_KC-222BKC-222B lube oil filter DP high

Recent goods issues

Never issued in the 17-month history.

Sparely