Sparely
DU

FILTER ELEMENT,FUEL GAS,5MICRON,P/N FE-4

Material 4100087119 · FILTER ELEMENT · Plant 1000

AReorderNormalSlow-moving
Material
4100087119
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 3 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
45 d · P80 47 d
Unit price
Rp 3.0M

Recommendation

  • 1.Forecast 8.5 EA/year: 8.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~45 days; expected demand during lead time 1.0.
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 13.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 11 now.
  • 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
11 EA
Rp 33.3M · order by 01 Oct 2026
Expected arrival ≈ 45 days
Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
13
order qty 7
Service level
99.8%
stockout risk now 10%
Unit price
Rp 3.0M
PO history
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 308 days ago, 9 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 3 functional locations

1 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-843
FUEL OIL COMPRESSOR
S1218.28
PX_KC-365C
INHIBITOR BLOWER
S173.14

Lead time and procurement

Lead time 45 ± 26 days (PO history, 3 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
21 Oct 2025PR03
Regular replenishment
1Rp 3.1M16 Nov 202526 d
15 Oct 2025PR06
Regular replenishment
2Rp 3.0M06 Dec 202552 d
14 Jul 2025PR03
Regular replenishment
2Rp 3.0M22 Aug 202539 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
21 Sept 2026MediumPX_KC-843Painting KC-843
16 Sept 2026LowPX_KC-843Inspect coupling KC-843
29 Aug 2026MediumPX_KC-843Replace lamp as per PM finding
26 Aug 2026MediumPX_KC-843[MSI-B-26-RLH-211] Permanent repair
14 Aug 2026MediumPX_KC-843KC-843 lube oil filter DP high
06 Aug 2026MediumPX_KC-843Replace lamp as per PM finding
02 Aug 2026EmergencyPX_KC-843[MSI-B-26-KRX-321] Permanent repair
26 Jul 2026MediumPX_KC-365CInspect coupling KC-365C
14 Jul 2026MediumPX_KC-843KC-843 bearing temp high

Recent goods issues

Posting dateQtyOrderOrder type
27 Nov 20252201000005269Corrective