BLADE,ROTOR,MODEL GJ662,SS316
Material 4100087966 · BLADE · Plant 1000
AReorderCriticalSlow-moving
- Material
- 4100087966
- Category
- BLADE
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (6 of 13 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 181 d · P80 263 d
- Unit price
- Rp 381.5M (est.)
Recommendation
- 1.Forecast 2.1 SET/year: 1.3 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~181 days; expected demand during lead time 1.4 (incl. 0.7 planned).
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 4 now.
- 5.Installed on 13 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 1.5B · order by 01 Oct 2026
Expected arrival ≈ 181 days
Needs Management sign-off before it reaches the PR draft
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
5
order qty 1
Service level
99.5%
stockout risk now 49%
Unit price
Rp 381.5M
Category + unit estimate
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 405 days ago, 9 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.
Installed on 13 functional locations
6 with criticality A/B · 16 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-460B TURBINE FOR KC-460B | A | 2 | 2 | 1.96 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KT-447 TURBINE FOR KC-447 | S | 3 | 13 | 6.24 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_KT-202 TURBINE FOR KC-202 | S | 1 | 4 | 2.81 |
| PX_KT-264A TURBINE FOR KC-264A | S | 1 | 4 | 2.39 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Aug 2025 | 1 | 204000021177 | Preventive |