BLADE,ROTOR,SIZE HR661,A182F11
Material 4100087984 · BLADE · Plant 1000
AReduceNon-moving
- Material
- 4100087984
- Category
- BLADE
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (4 of 9 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 181 d · P80 263 d
- Unit price
- Rp 381.5M (est.)
Recommendation
- 1.Forecast 1.7 SET/year: 0.9 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~181 days; expected demand during lead time 1.2 (incl. 0.7 planned).
- 3.A 98.8% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 4.
- 4.Stock 63 exceeds the level to keep (4) by 59.
- 5.Installed on 9 FuncLoc(s), 4 of them criticality A/B.
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
63 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 2
Rec. Max
4
order qty 1
Service level
98.8%
stockout risk now 0%
Unit price
Rp 381.5M
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 4 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.
Installed on 9 functional locations
4 with criticality A/B · 15 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-419A TURBINE FOR KC-419A | A | 3 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-513 TURBINE FOR KC-513 | A | 3 | 2 | 1.53 |
| PX_KT-447 TURBINE FOR KC-447 | S | 1 | 13 | 6.24 |
| PX_KT-264A TURBINE FOR KC-264A | S | 1 | 4 | 2.39 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
| PX_KT-778A TURBINE FOR KC-778A | S | 3 | 0 | 1.10 |
| PX_KT-875 TURBINE FOR KC-875 | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 11 Jun 2026 | Low | PX_KT-264A | Leak from packing |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 13 May 2026 | Low | PX_KT-447 | KT-447 trip test |
| 21 Apr 2026 | Low | PX_KT-264A | Follow up after steam upset KT-264A |
Recent goods issues
Never issued in the 17-month history.