BLADE,ROTOR,MODEL RY258,A105
Material 4100088003 · BLADE · Plant 1000
AMonitorInsurance gap
- Material
- 4100088003
- Category
- BLADE
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- DUTA SEJAHTERA ABADI PT
- Lead time
- 181 d · P80 263 d
- Unit price
- Rp 549.7M
Recommendation
- 1.Forecast 0.5 SET/year: 0.5 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~181 days; expected demand during lead time 0.3.
- 3.A 97.2% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Insurance spare candidateSingle sourceOpen POLead time estimated
On hand / on order
0 / 1
next delivery 23 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
97.2%
stockout risk now 3%
Unit price
Rp 549.7M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.
Installed on 5 functional locations
4 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-460B TURBINE FOR KC-460B | A | 1 | 2 | 1.96 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
Lead time and procurement
Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 18 May 2025 | PR01 Import / long-lead | 1 | Rp 549.7M | 23 Nov 2026 open | 554 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 02 Apr 2026 | Medium | PX_KT-397A | Follow up after steam upset KT-397A |
| 26 Mar 2026 | Medium | PX_KT-856A | KT-856A steam leak at gland |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 07 Feb 2026 | Medium | PX_KT-624A | Replace lamp as per PM finding |
Recent goods issues
Never issued in the 17-month history.