BLADE,ROTOR,MODEL RY258,A105

Material 4100088003 · BLADE · Plant 1000

AMonitorInsurance gap
Material
4100088003
Category
BLADE
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 5 FuncLocs A/B)
Supplier
DUTA SEJAHTERA ABADI PT
Lead time
181 d · P80 263 d
Unit price
Rp 549.7M

Recommendation

  • 1.Forecast 0.5 SET/year: 0.5 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~181 days; expected demand during lead time 0.3.
  • 3.A 97.2% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Insurance spare candidateSingle sourceOpen POLead time estimated
On hand / on order
0 / 1
next delivery 23 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
97.2%
stockout risk now 3%
Unit price
Rp 549.7M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.

Installed on 5 functional locations

4 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-624A
TURBINE FOR KC-624A
S132.39

Lead time and procurement

Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
18 May 2025PR01
Import / long-lead
1Rp 549.7M23 Nov 2026
open
554 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A
26 Mar 2026MediumPX_KT-856AKT-856A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
07 Feb 2026MediumPX_KT-624AReplace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.