BLADE,ROTOR,MODEL UI440,A105
Material 4100088078 · BLADE · Plant 1000
AReduceExcess
- Material
- 4100088078
- Category
- BLADE
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 181 d · P80 263 d
- Unit price
- Rp 381.5M (est.)
Recommendation
- 1.Forecast 4.2 SET/year: 4.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~181 days; expected demand during lead time 2.1.
- 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 7.
- 4.Stock 22 exceeds the level to keep (7) by 15.
- 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
22 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 4
Rec. Max
7
order qty 1
Service level
99.5%
stockout risk now 0%
Unit price
Rp 381.5M
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 20 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 8.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.
Installed on 5 functional locations
2 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KT-383A TURBINE FOR KC-383A | S | 2 | 7 | 3.67 |
| PX_KT-202 TURBINE FOR KC-202 | S | 3 | 4 | 2.81 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
Lead time and procurement
Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 26 Mar 2026 | Medium | PX_KT-856A | KT-856A steam leak at gland |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 11 Sept 2026 | 1 | 201000021470 | Corrective |