BLADE,ROTOR,TYPE NV816,A105
Material 4100088346 · BLADE · Plant 1000
AReduceNon-moving
- Material
- 4100088346
- Category
- BLADE
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 181 d · P80 263 d
- Unit price
- Rp 381.5M (est.)
Recommendation
- 1.Forecast 0.2 SET/year: 0.2 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~181 days; expected demand during lead time 0.1.
- 3.A 92.4% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Stock 5 exceeds the level to keep (1) by 4.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
92.4%
stockout risk now 0%
Unit price
Rp 381.5M
Category + unit estimate
ML early warning: 0% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 338.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 181 ± 109 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 16 May 2026 | Medium | PX_KT-397A | Replace lamp as per PM finding |
| 14 May 2026 | Low | PX_KT-397A | KT-397A trip test |
| 02 Apr 2026 | Medium | PX_KT-397A | Follow up after steam upset KT-397A |
| 10 May 2025 | Medium | PX_KT-397A | Leak from packing |
Recent goods issues
Never issued in the 17-month history.