BLADE,ROTOR,MODEL PD172,CS

Material 4100088684 · BLADE · Plant 1000

ALong-leadReduceSlow-moving
Material
4100088684
Category
BLADE
Base unit
SET
MRP type
Stock Item
Criticality
A (1 of 1 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
207 d · P80 263 d
Unit price
Rp 209.2M

Recommendation

  • 1.Forecast 1.0 SET/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~207 days; expected demand during lead time 0.6.
  • 3.A 98.1% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 6 exceeds the level to keep (3) by 3.
  • 5.Long lead time: 80% of deliveries took up to 263 days and the fastest seen in its category 99 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
6 / 2
next delivery 22 Nov 2026
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
98.1%
stockout risk now 0%
Unit price
Rp 209.2M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 297 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~99 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81

Lead time and procurement

Lead time 207 ± 109 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
09 Feb 2026PR03
Regular replenishment
2Rp 209.2M22 Nov 2026
open
286 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
26 Mar 2026MediumPX_KT-856AKT-856A steam leak at gland
20 Nov 2025MediumPX_KT-856AKT-856A governor valve hunting
16 Nov 2025LowPX_KT-856AInstall scaffolding at KT-856A
04 Sept 2025LowPX_KT-856AInstall scaffolding at KT-856A
26 Aug 2025LowPX_KT-856AReplace lamp as per PM finding
09 May 2025MediumPX_KT-856APSM25/KT-856A steam leak at gland

Recent goods issues

Posting dateQtyOrderOrder type
08 Dec 20251201000025971Corrective