VALVE,GOVERNOR,MODEL MW912,MONEL

Material 4100089724 · VALVE · Plant 1000

AMonitorInsurance gap
Material
4100089724
Category
VALVE
Base unit
ASS
MRP type
Non Stock
Criticality
A (6 of 13 FuncLocs A/B)
Supplier
No PO history
Lead time
47 d · P80 92 d
Unit price
Rp 238.3M (est.)

Recommendation

  • 1.Forecast 1.3 ASS/year: 1.3 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~47 days; expected demand during lead time 0.2.
  • 3.A 98.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 13 FuncLoc(s), 6 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.7%
stockout risk now 16%
Unit price
Rp 238.3M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 9 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 570.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 13 functional locations

6 with criticality A/B · 13 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-383A
TURBINE FOR KC-383A
S173.67
PX_KT-202
TURBINE FOR KC-202
S142.81
PX_KT-264A
TURBINE FOR KC-264A
S142.39
PX_KT-624A
TURBINE FOR KC-624A
S132.39
PX_KT-778A
TURBINE FOR KC-778A
S101.10

Lead time and procurement

Lead time 47 ± 30 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding

Recent goods issues

Never issued in the 17-month history.