VALVE,GOVERNOR,SIZE YP943,MONEL

Material 4100089807 · VALVE · Plant 1000

AMaintainStockout
Material
4100089807
Category
VALVE
Base unit
ASS
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
47 d · P80 92 d
Unit price
Rp 204.2M

Recommendation

  • 1.Forecast 2.3 ASS/year: 2.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~47 days; expected demand during lead time 0.3.
  • 3.A 96.3% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Single sourceOpen POLead time estimated
On hand / on order
0 / 6
next delivery 22 Dec 2027
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
96.3%
stockout risk now 0%
Unit price
Rp 204.2M
PO history
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 29 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 989.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KT-875
TURBINE FOR KC-875
S101.10

Lead time and procurement

Lead time 47 ± 30 days (Category estimate, 0 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
12 Apr 2026PR03
Regular replenishment
2Rp 204.2M19 Jul 2028
open
829 d
20 Mar 2026PR03
Regular replenishment
2Rp 196.7M22 Dec 2027
open
642 d
27 Sept 2025PR03
Regular replenishment
2Rp 211.0M04 Jan 2028
open
829 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
26 Mar 2026MediumPX_KT-856AKT-856A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KT-419ALeak from packing
20 Nov 2025MediumPX_KT-856AKT-856A governor valve hunting
16 Nov 2025LowPX_KT-856AInstall scaffolding at KT-856A
10 Nov 2025MediumPX_KT-419APainting KT-419A
04 Sept 2025LowPX_KT-856AInstall scaffolding at KT-856A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A

Recent goods issues

Posting dateQtyOrderOrder type
02 Sept 20261201000024663Corrective
20 Jul 20251205000012589Other maintenance