VALVE,GOVERNOR,TYPE NC948,A105
Material 4100089858 · VALVE · Plant 1000
ALong-leadReduceExcess
- Material
- 4100089858
- Category
- VALVE
- Base unit
- ASS
- MRP type
- Stock Item
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- RAJAWALI REFRAKTORI PRATAMA PT
- Lead time
- 120 d · P80 92 d
- Unit price
- Rp 186.7M
Recommendation
- 1.Forecast 2.3 ASS/year: 2.3 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~120 days; expected demand during lead time 0.8.
- 3.A 95.7% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Stock 5 exceeds the level to keep (3) by 2.
- 5.Long lead time: 80% of deliveries took up to 92 days and the fastest seen in its category 20 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
5 / 2
next delivery 15 Oct 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
95.7%
stockout risk now 0%
Unit price
Rp 186.7M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 9 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 991.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_KT-778A TURBINE FOR KC-778A | S | 1 | 0 | 1.10 |
Lead time and procurement
Lead time 120 ± 30 days (PO history + category, 2 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 08 Jul 2026 | PR03 Regular replenishment | 2 | Rp 195.8M | 15 Oct 2027 open | 464 d |
| 20 Jan 2026 | PR03 Regular replenishment | 1 | Rp 184.1M | 18 Aug 2026 | 210 d |
| 11 Sept 2025 | PR03 Regular replenishment | 1 | Rp 186.7M | 20 May 2026 | 251 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
| 04 Jan 2026 | Medium | PX_KT-513 | KT-513 governor valve hunting |
| 23 Jun 2025 | Medium | PX_KT-383A | KT-383A governor valve hunting |
| 03 May 2025 | Medium | PX_KT-513 | KT-513 governor valve hunting |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Sept 2026 | 1 | 201000039118 | Corrective |