VALVE,GOVERNOR,SIZE LD214,SS304
Material 4100091202 · VALVE · Plant 1000
AMonitorInsurance gap
- Material
- 4100091202
- Category
- VALVE
- Base unit
- ASS
- MRP type
- Non Stock
- Criticality
- A (1 of 3 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 47 d · P80 92 d
- Unit price
- Rp 238.3M (est.)
Recommendation
- 1.Forecast 0.4 ASS/year: 0.4 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~47 days; expected demand during lead time 0.1.
- 3.A 95.0% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
95.0%
stockout risk now 5%
Unit price
Rp 238.3M
Category + unit estimate
ML early warning: 1% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 169.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~20 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_KT-447 TURBINE FOR KC-447 | S | 1 | 13 | 6.24 |
| PX_KT-624A TURBINE FOR KC-624A | S | 1 | 3 | 2.39 |
Lead time and procurement
Lead time 47 ± 30 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 13 May 2026 | Low | PX_KT-447 | KT-447 trip test |
| 19 Apr 2026 | Low | PX_KT-447 | Follow up after steam upset KT-447 |
| 30 Mar 2026 | Low | PX_KT-447 | Leak from packing |
| 28 Mar 2026 | Medium | PX_KT-447 | Follow up after steam upset KT-447 |
| 14 Mar 2026 | Medium | PX_KT-447 | KT-447 steam leak at gland |
| 07 Feb 2026 | Medium | PX_KT-624A | Replace lamp as per PM finding |
| 14 Jan 2026 | Medium | PX_KT-447 | Follow up after steam upset KT-447 |
Recent goods issues
Never issued in the 17-month history.