GREASE,COMPLEX,NLGI 2,180KG

Material 4100091448 · GREASE · Plant 1000

AReduceExcess
Material
4100091448
Category
GREASE
Base unit
KG
MRP type
Stock Item
Criticality
A (9 of 16 FuncLocs A/B)
Supplier
GEMILANG TEKNIK LESTARI PT
Lead time
47 d · P80 61 d
Unit price
Rp 90,747

Recommendation

  • 1.Forecast 13,281 KG/year: 13,245 unplanned (recency-weighted compound poisson (own history)) + 36 from the maintenance plan.
  • 2.Lead time ~47 days; expected demand during lead time 1,709.
  • 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 4,988, order up to 6,470.
  • 4.Stock 22,300 exceeds the level to keep (12,900) by 9,400; the level includes the 12,900 used in the last turnaround.
  • 5.Installed on 16 FuncLoc(s), 9 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 12,900Single sourceAbnormal consumptionOpen POSame description as 1 other material number
On hand / on order
22,300 / 102,030
next delivery 08 Oct 2026
Today Min / Max
2,000 / 3,344
static parameters in BoM
Rec. Min (reorder point)
4,988
safety stock 3,279
Rec. Max
6,470
order qty 1,482
Service level
99.5%
stockout risk now 0%
Unit price
Rp 90,747
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 36 issue days in the last 180 days, last issue 1 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 14 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (14,175 units) excluded from the baseline.

Demand pattern Erratic · 142 issue days · 28 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 25.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.

Installed on 16 functional locations

9 with criticality A/B · 13,175 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1143B-M
MOTOR FOR PP-1143B
A50000.19
PX_PP-1323A-M
MOTOR FOR PP-1323A
A1,20000.19
PX_PP-1977-M
MOTOR FOR PP-1977
A20000.19
PX_PP-471B-M
MOTOR FOR PP-471B
A2500.19
PX_PP-506A-M
MOTOR FOR PP-506A
A50000.19
PX_PP-657C-M
MOTOR FOR PP-657C
A3,00000.19
PX_KC-373B-M
MOTOR FOR KC-373B
B20021.43
PX_PP-149-M
MOTOR FOR PP-149
B2500.19
PX_PP-1612-M
MOTOR FOR PP-1612
B50000.19
PX_PP-479-M
MOTOR FOR PP-479
C1,20030.62
PX_PP-1106A-M
MOTOR FOR PP-1106A
C20000.19
PX_PP-1202-M
MOTOR FOR PP-1202
C1,20000.19

Lead time and procurement

Lead time 47 ± 30 days (PO history, 46 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
16 Sept 2026PR03
Regular replenishment
27,091Rp 88,35911 Oct 2026
open
25 d
27 Aug 2026PR01
Import / long-lead
36,818Rp 87,79310 Mar 2027
open
195 d
27 Aug 2026PR03
Regular replenishment
38,121Rp 88,56608 Oct 2026
open
42 d
11 Jul 2026PR03
Regular replenishment
56,516Rp 91,99816 Aug 202636 d
27 Jun 2026PR03
Regular replenishment
47,802Rp 88,52620 Aug 202654 d
26 Jun 2026PR06
Regular replenishment
48,209Rp 90,61029 Jul 202633 d
17 Jun 2026PR03
Regular replenishment
46,333Rp 94,87519 Jul 202632 d
12 Jun 2026PR05
Project / turnaround
53,618Rp 90,71701 Aug 202650 d
08 Jun 2026PR03
Regular replenishment
17,613Rp 94,80511 Jul 202633 d
05 May 2026PR03
Regular replenishment
18,857Rp 93,18826 Jun 202652 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PP-471B-MRe-greasing Bearing Motor17.9
02 Jun 2027PX_PP-471B-MRe-greasing Bearing Motor17.9

Recent notifications on its equipment

DatePriorityFuncLocDescription
20 Jan 2026MediumPX_PP-479-MPainting PP-479-M
21 Nov 2025MediumPX_PP-479-MReplace lamp as per PM finding
14 Nov 2025MediumPX_KC-373B-MMegger test KC-373B-M
08 Aug 2025MediumPX_KC-373B-M[MSI-B-25-LSB-196] Permanent repair
22 May 2025LowPX_PP-479-MMegger test PP-479-M

Recent goods issues

Posting dateQtyOrderOrder type
30 Sept 202650201000001081Corrective
30 Sept 202650201000012524Corrective
30 Sept 202650201000015377Corrective
30 Sept 202625201000024007Corrective
28 Sept 202625201000018157Corrective
27 Sept 202625209000029477Other maintenance
23 Sept 202625209000029477Other maintenance
18 Sept 202625201000003432Corrective
05 Sept 202650201000000202Corrective
05 Sept 202625201000003235Corrective
31 Aug 202625204000022675Preventive
28 Aug 20261,000201000007926Corrective
28 Aug 202625201000016249Corrective
23 Aug 202625201000023643Corrective
22 Aug 202625201000015928Corrective