GREASE,LITHIUM,NLGI 2,16KG
Material 4100091603 · GREASE · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100091603
- Category
- GREASE
- Base unit
- KG
- MRP type
- Stock Item
- Criticality
- A (4 of 5 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 31 d · P80 51 d
- Unit price
- Rp 91,907
Recommendation
- 1.Forecast 4,498 KG/year: 77 unplanned (credibility blend: own history + installed-base prior) + 4,421 from the maintenance plan.
- 2.Lead time ~31 days; expected demand during lead time 24 (incl. 18 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 218, order up to 1,075.
- 4.On hand 38 + on order 0 is at or below the reorder point: order 1,037 now.
- 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
1,037 KG
Rp 95.3M · order by 01 Oct 2026
Expected arrival ≈ 31 days
Single sourcePlanned demand in lead time
On hand / on order
38 / 0
no open PO
Today Min / Max
13 / 32
static parameters in BoM
Rec. Min (reorder point)
218
safety stock 194
Rec. Max
1,075
order qty 857
Service level
99.9%
stockout risk now 3%
Unit price
Rp 91,907
PO history
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 333 days ago, 0 failure notifications on its equipment in 90 days, 3 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 108.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 5 functional locations
4 with criticality A/B · 3,125 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1013A-M MOTOR FOR PP-1013A | A | 3,000 | 0 | 0.19 |
| PX_PP-439B-M MOTOR FOR PP-439B | A | 25 | 0 | 0.19 |
| PX_PP-837-M MOTOR FOR PP-837 | A | 25 | 0 | 0.19 |
| PX_MOV-903A MOTOR OPERATED GATE VALVE | B | 25 | 0 | 0.06 |
| PX_PP-224-M MOTOR FOR PP-224 | C | 50 | 0 | 0.19 |
Lead time and procurement
Lead time 31 ± 18 days (PO history + category, 1 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 08 Oct 2025 | PR06 Regular replenishment | 87 | Rp 91,907 | 13 Nov 2025 | 36 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Oct 2026 | PX_PP-837-M | Re-greasing Bearing Motor | 17.9 |
| 01 Nov 2026 | PX_MOV-903A | Re-greasing Gear Box MOV | 17.9 |
| 30 Nov 2026 | PX_PP-1013A-M | Re-greasing Bearing Motor | 2,148 |
| 30 Mar 2027 | PX_PP-224-M | Re-greasing Bearing Motor | 35.8 |
| 02 Apr 2027 | PX_PP-837-M | Re-greasing Bearing Motor | 17.9 |
| 31 May 2027 | PX_PP-1013A-M | Re-greasing Bearing Motor | 2,148 |
| 28 Sept 2027 | PX_PP-224-M | Re-greasing Bearing Motor | 35.8 |
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 Nov 2025 | 200 | 201000029932 | Corrective |