TUBE PLUG,EXCHANGER,SIZE DA178,A105
Material 4100093415 · TUBE PLUG · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100093415
- Category
- TUBE PLUG
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 9 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 77 d · P80 151 d
- Unit price
- Rp 505,158 (est.)
Recommendation
- 1.Forecast 3.8 EA/year: 3.8 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~77 days; expected demand during lead time 0.8.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 10.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 8 now.
- 5.Installed on 9 FuncLoc(s), 6 of them criticality A/B.
Proposed purchase requisition
8 EA
Rp 4.0M · order by 01 Oct 2026
Expected arrival ≈ 77 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
10
order qty 4
Service level
99.9%
stockout risk now 6%
Unit price
Rp 505,158
Category + unit estimate
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 41 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~29 days.
Installed on 9 functional locations
6 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_HE-538B GASOLINE REBOILER | A | 1 | 2 | 0.65 |
| PX_HE-1768 GASOLINE EXCHANGER | A | 1 | 1 | 0.65 |
| PX_HE-708A SLOP OIL COOLER | A | 1 | 1 | 0.22 |
| PX_HE-895B DEMIN WATER EXCHANGER | A | 1 | 0 | 0.22 |
| PX_HE-1874C METHANOL COOLER | B | 1 | 3 | 1.08 |
| PY_HE-1685D QUENCH OIL CONDENSER | B | 1 | 1 | 0.65 |
| PX_HE-239D RECYCLE ETHANE TLE | C | 4 | 5 | 1.08 |
| PX_HE-1772B SLOP OIL PREHEATER | C | 1 | 0 | 0.22 |
| PX_HE-844A SEAL OIL TLE | C | 1 | 0 | 0.22 |
Lead time and procurement
Lead time 77 ± 62 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 16 Aug 2026 | Medium | PX_HE-239D | Replace lamp as per PM finding |
| 08 Jul 2026 | Medium | PX_HE-1874C | Replace lamp as per PM finding |
| 03 Mar 2026 | Medium | PX_HE-1874C | Leak from packing |
| 19 Feb 2026 | High | PX_HE-538B | HE-538B tube leak |
| 09 Feb 2026 | Low | PX_HE-239D | Install scaffolding at HE-239D |
| 04 Nov 2025 | Medium | PX_HE-239D | Replace lamp as per PM finding |
| 25 Oct 2025 | Emergency | PX_HE-239D | Install scaffolding at HE-239D |
| 30 Jul 2025 | High | PY_HE-1685D | Leak from packing |
| 29 Jun 2025 | Low | PX_HE-1768 | [MSI-B-25-FUE-333/M] Replace line |
| 27 May 2025 | Medium | PX_HE-239D | HE-239D tube leak |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Aug 2026 | 3 | 201000007325 | Corrective |
| 30 May 2025 | 1 | 201000003161 | Corrective |