TUBE PLUG,EXCHANGER,SIZE LW281,SS304

Material 4100093458 · TUBE PLUG · Plant 1000

ALong-leadReorderNormalBelow reorder point
Material
4100093458
Category
TUBE PLUG
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 5 FuncLocs A/B)
Supplier
SAMUDRA SEJAHTERA INTERNASIONAL PT
Lead time
85 d · P80 151 d
Unit price
Rp 1.6M

Recommendation

  • 1.Forecast 2.4 EA/year: 2.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~85 days; expected demand during lead time 0.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 151 days and the fastest seen in its category 29 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 5 FuncLoc(s), 5 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 9.6M · order by 01 Oct 2026
Expected arrival ≈ 85 days
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
9
order qty 3
Service level
100.0%
stockout risk now 3%
Unit price
Rp 1.6M
PO history
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 45 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 741.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~29 days.

Installed on 5 functional locations

5 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-1797C
FUEL OIL PREHEATER
A100.22
PX_HE-931B
ETHYLENE CONDENSER
A100.22
PX_HE-1751C
FLUSHING OIL COOLER
B220.65
PX_HE-1482D
ETHYLENE TLE
B300.22
PX_HE-263B
RICH AMINE TLE
B100.22

Lead time and procurement

Lead time 85 ± 62 days (PO history + category, 2 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
27 May 2026PR03
Regular replenishment
1Rp 1.6M13 Sept 2026109 d
01 Oct 2025PR06
Regular replenishment
2Rp 1.6M27 Dec 202587 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
05 Dec 2025MediumPX_HE-1751CRetubing HE-1751C
18 May 2025MediumPX_HE-1751CInstall scaffolding at HE-1751C

Recent goods issues

Posting dateQtyOrderOrder type
17 Aug 20262201000037592Corrective
17 Aug 20261201000037592Corrective
10 Sept 20251201000025945Corrective